10-Inch & 8-Inch NGL Pipeline Project - McKenzie

From the ProvenHand pipeline wiki

10-Inch & 8-Inch NGL Pipeline Project - McKenzie is a pipeline project in North Dakota, operated by Arrow Field Services, LLC. Construction began in 2017. It runs 2.6 miles of 8", 10" pipe.

10-Inch & 8-Inch NGL Pipeline Project - McKenzie
General information
KindPipeline project[1]
Project typeNew build[2]
StatusIn service[3]
Owner and operator
StateNorth Dakota[1]
CountiesMcKenzie[2]
Approved30 June 2017[2]
Construction started25 August 2017[4]
North Dakota PSC casePU-17-048[1]
Technical information
Length2.6 mi[2]
Pipe size8", 10"[2]
Costtotal anticipated cost of the Project is approximately $6.3 million[2]
On ProvenHand
Hands listed0

10-Inch & 8-Inch NGL Pipeline Project - McKenzie is a pipeline project in North Dakota, operated by Arrow Field Services, LLC. Construction began in 2017. It runs 2.6 miles of 8", 10" pipe.

Inspection

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on 10-Inch & 8-Inch NGL Pipeline Project - McKenzie? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “North Dakota Public Service Commission: case search (pipeline siting)”. North Dakota Public Service Commission. Retrieved 3 October 2026.
  2. “Order on Recommended Findings of Fact, Conclusions of Law and Order, Case No. PU-17-48 (Arrow 10-inch residue gas and 8-inch NGL pipelines)”. North Dakota Public Service Commission. 30 June 2017. Retrieved 3 October 2026.
  3. “As-built Construction Inspection Report, PSC Case No. PU-17-48”. Bartlett & West, Inc. (filed with the North Dakota Public Service Commission). 6 December 2017. Retrieved 3 October 2026.
  4. “Topsoil Removal Inspection Report, PSC Case No. PU-17-48”. Bartlett & West, Inc. (filed with the North Dakota Public Service Commission). 7 September 2017. Retrieved 3 October 2026.
  5. “Purchase of service contract for construction inspection, Case No. PU-17-48”. North Dakota Public Service Commission. 26 July 2017. Retrieved 3 October 2026.