2021 Lucas and Pavonia New Wells Project
From the ProvenHand pipeline wiki
2021 Lucas and Pavonia New Wells Project is a natural gas facility project in Ohio, operated by Columbia Gas Transmission, LLC. Construction began in 2021.
| 2021 Lucas and Pavonia New Wells Project | |
|---|---|
| General information | |
| Kind | Facility project[1] |
| Project type | New build[2] |
| Status | In service[3] |
| Commodity | Natural gas[2] |
| Owner and operator | |
| State | Ohio[1] |
| Counties | Ashland, Richland[1] |
| Construction started | 23 September 2021[5] |
| FERC docket | CP21-473[4] |
| Contractors | |
| Technical information | |
| Cost | $15,000,000[1] |
| On ProvenHand | |
| Hands listed | 0 |
2021 Lucas and Pavonia New Wells Project is a natural gas facility project in Ohio, operated by Columbia Gas Transmission, LLC. Construction began in 2021.
Contractorsedit
| Contractor | Work |
|---|---|
| Workhorse Trucking & Excavating[5] | well-site construction contractor (mobilized equipment to the new well locations) |
| Newpark Mats & Integrated Services[5] | ground protection / rig matting in temporary workspace |
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on 2021 Lucas and Pavonia New Wells Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “Environmental Assessment Report, 2021 Lucas and Pavonia New Wells Project (CP21-473)”. FERC. 15 September 2021. Retrieved 4 October 2026.
- “Notice of Request Under Blanket Authorization, Columbia Gas Transmission, LLC (CP21-473)”. Federal Energy Regulatory Commission. 23 July 2021. Retrieved 4 October 2026.
- “Final Weekly Environmental Inspector Report No. 13, 2021 Lucas and Pavonia New Wells Project (CP21-473)”. Columbia Gas Transmission, LLC (filed with FERC). 7 January 2022. Retrieved 4 October 2026.
- “FERC eLibrary docket CP21-473”. Federal Energy Regulatory Commission. 16 July 2021. Retrieved 3 October 2026.
- “Weekly Environmental Inspector Report No. 1, 2021 Lucas and Pavonia New Wells Project (CP21-473)”. Columbia Gas Transmission, LLC (filed with FERC). 30 September 2021. Retrieved 4 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.