24-Inch Crude Oil Pipeline - McKenzie County
From the ProvenHand pipeline wiki
24-Inch Crude Oil Pipeline - McKenzie County is a crude oil pipeline in North Dakota, operated by Plains Terminals North Dakota LLC. Construction began in 2017. It runs 3.5 miles of 16" pipe.
| 24-Inch Crude Oil Pipeline - McKenzie County | |
|---|---|
| General information | |
| Kind | Pipeline project[1] |
| Project type | New build[2] |
| Status | In service[3] |
| Commodity | Crude oil[2] |
| Owner and operator | |
| State | North Dakota[1] |
| Counties | McKenzie[2] |
| Approved | 17 August 2016[2] |
| Construction started | August 2017[4] |
| North Dakota PSC case | PU-16-140[1] |
| Contractors | |
| Technical information | |
| Length | 3.5 mi[2] |
| Pipe size | 16"[2] |
| Capacity | maximum capacity of the Project will be 150,000 barrels per day[2] |
| Cost | total cost of the Project is estimated to be $5 million[2] |
| On ProvenHand | |
| Hands listed | 0 |
24-Inch Crude Oil Pipeline - McKenzie County is a crude oil pipeline in North Dakota, operated by Plains Terminals North Dakota LLC. Construction began in 2017. It runs 3.5 miles of 16" pipe.
Contractorsedit
| Contractor | Work |
|---|---|
| E3 Environmental, LLC[5] | environmental consulting (listed as Sr. Env. Consultant in the pre-construction minutes) |
Inspection
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on 24-Inch Crude Oil Pipeline - McKenzie County? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “North Dakota Public Service Commission: case search (pipeline siting)”. North Dakota Public Service Commission. Retrieved 3 October 2026.
- “Order on Recommended Findings of Fact, Conclusions of Law and Order, Case No. PU-16-140 (Plains Terminals North Dakota, Johnsons Corner pipeline)”. North Dakota Public Service Commission. 17 August 2016. Retrieved 3 October 2026.
- “As-Built Inspection Report (field visits November 2017), Plains Johnsons Corner to Dakota Access pipeline, PU-16-140”. KLJ Solutions Co. (filed with the North Dakota Public Service Commission). 27 August 2019. Retrieved 3 October 2026.
- “Topsoil Inspection Report (field visits August 2017), Plains Johnsons Corner to Dakota Access pipeline, PU-16-140”. KLJ Solutions Co. (filed with the North Dakota Public Service Commission). 27 August 2019. Retrieved 3 October 2026.
- “Preconstruction meeting minutes (2017-07-25) and notice of construction commencement, Plains Terminals North Dakota, PU-16-140”. Plains Terminals North Dakota LLC (filed with the North Dakota Public Service Commission). 1 August 2017. Retrieved 3 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.