8-inch Crude Oil Pipeline - McKenzie County

From the ProvenHand pipeline wiki

8-inch Crude Oil Pipeline - McKenzie County is a crude oil pipeline in North Dakota, operated by Bridger Pipeline LLC. Construction began in 2021.

8-inch Crude Oil Pipeline - McKenzie County
Also calledJohnson's Corner to Wilson Pipeline Project[1]
General information
KindPipeline project[2]
StatusIn service[3]
CommodityCrude oil[4]
Owner and operator
StateNorth Dakota[2]
CountiesMcKenzie[4]
Approved19 May 2021[4]
Construction started29 November 2021[5]
North Dakota PSC casePU-20-430[2]
Contractors
Technical information
Pipe size8"[4]
Costestimated cost of the Project is $21 million[4]
On ProvenHand
Hands listed0

8-inch Crude Oil Pipeline - McKenzie County is a crude oil pipeline in North Dakota, operated by Bridger Pipeline LLC. Construction began in 2021.

Contractorsedit

ContractorWorkPrime or sub
Loenbro Pipeline LLC[6]Prime
Dirty Birds LLC[5]subcontractor to Loenbro Pipeline LLC (scope not stated in the daily report)Under Loenbro Pipeline LLC

Inspection

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on 8-inch Crude Oil Pipeline - McKenzie County? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “Pre-Construction Conference Meeting Minutes (2021-11-10), Johnson's Corner to Wilson Pipeline Project, PU-20-430”. Bridger Pipeline LLC (filed with the North Dakota Public Service Commission). 11 November 2021. Retrieved 4 October 2026.
  2. “North Dakota Public Service Commission: case search (pipeline siting)”. North Dakota Public Service Commission. Retrieved 3 October 2026.
  3. “2.4-mile As-Built Construction Inspection Report, Bridger 8-inch Crude Oil Pipeline, PU-20-430”. Short Elliott Hendrickson Inc. (filed with the North Dakota Public Service Commission). 7 October 2022. Retrieved 3 October 2026.
  4. “Findings of Fact, Conclusions of Law and Order, Case No. PU-20-430 (Bridger 8-inch crude oil pipeline, McKenzie County)”. North Dakota Public Service Commission. 19 May 2021. Retrieved 3 October 2026.
  5. “Topsoil Removal Inspection Report, Bridger 8-inch Crude Oil Pipeline, PU-20-430”. Short Elliott Hendrickson Inc. (filed with the North Dakota Public Service Commission). 20 December 2021. Retrieved 3 October 2026.
  6. “Construction Inspection Report, Bridger 8-inch Crude Oil Pipeline, PU-20-430”. Short Elliott Hendrickson Inc. (filed with the North Dakota Public Service Commission). 30 December 2021. Retrieved 3 October 2026.
  7. “Purchase of service contract for construction inspection, Case No. PU-20-430”. North Dakota Public Service Commission. 11 June 2021. Retrieved 3 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.