Algonquin Gas Transmission J-2 Loop Project
From the ProvenHand pipeline wiki
Algonquin Gas Transmission J-2 Loop Project is a natural gas pipeline in Massachusetts, operated by Algonquin Gas Transmission, LLC. It was built and entered service in 2009. It runs 2.3 miles of 14" pipe.
| Algonquin Gas Transmission J-2 Loop Project | |
|---|---|
| Also called | Algonquin J-2 Loop[1] |
| General information | |
| Kind | Pipeline project[2] |
| Project type | Expansion[1] or Loop[3][sources disagree] |
| Status | In service[1][4] |
| Commodity | Natural gas[1] |
| Owner and operator | |
| State | Massachusetts[1][2] |
| Approved | 11 February 2009[2][5] |
| Construction started | 5 May 2009[6] |
| In service | 2 September 2009[1][4] |
| FERC docket | CP08-256[2] |
| Technical information | |
| Length | 2.3 mi[1][2] |
| Pipe size | 14"[1] |
| Capacity | 140 MMcf/d (FERC project list)[1][2] |
| Cost | $34.5 million (EIA estimate; no dollar year given)[1] |
| On ProvenHand | |
| Hands listed | 0 |
Algonquin Gas Transmission J-2 Loop Project is a natural gas pipeline in Massachusetts, operated by Algonquin Gas Transmission, LLC. It was built and entered service in 2009. It runs 2.3 miles of 14" pipe.
Sources disagree
These sources give different values for the same fact. Each value is listed with the sources that give it.
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Algonquin Gas Transmission J-2 Loop Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
- “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
- “FERC eLibrary docket CP08-256”. Federal Energy Regulatory Commission. 30 April 2008. Retrieved 3 October 2026.
- “Corrected Notice of Commencement of Service, J-2 Loop Project (CP08-256)”. Algonquin Gas Transmission, LLC (filed with FERC). 2 October 2009. Retrieved 4 October 2026.
- “Order issuing certificate re Algonquin Gas Transmission, LLC (CP08-256), eLibrary filing description”. FERC. 11 February 2009. Retrieved 4 October 2026.
- “Notice of Commencement of Construction for J-2 Loop Project (CP08-256)”. Algonquin Gas Transmission, LLC (filed with FERC). 5 May 2009. Retrieved 4 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.