Appalachia to Market II & Armagh & Entriken HP Replacement Project

From the ProvenHand pipeline wiki

Sources disagree on some of this page's facts. Each value is shown with its sources; see Sources disagree.

Appalachia to Market II & Armagh & Entriken HP Replacement Project is a natural gas pipeline replacement in New Jersey and Pennsylvania, operated by Texas Eastern Transmission, LP. Construction began in 2024. It runs 2 miles of 36" pipe.

Appalachia to Market II & Armagh & Entriken HP Replacement Project
General information
KindPipeline project[1]
Project typeReplacement[1][2]
StatusUnder construction[2][3]
CommodityNatural gas[2]
Owner and operator
Facility projects
StatesNew Jersey, Pennsylvania[2][4]
CountiesHuntingdon, Indiana, Lebanon[5]
Approved23 October 2023[4][5]
Construction startedMarch 2024[6]
FERC docketCP22-486[1]
Technical information
Length2 mi[2][4][5]
Pipe size36"[2][5]
Capacity55 MMcf/d (FERC project list)[2][4]
Cost$368 million (EIA estimate; no dollar year given)[2] or $368,729,684 estimated total cost of the projects (certificate order)[5][sources disagree]
On ProvenHand
Hands listed0

Appalachia to Market II & Armagh & Entriken HP Replacement Project is a natural gas pipeline replacement in New Jersey and Pennsylvania, operated by Texas Eastern Transmission, LP. Construction began in 2024. It runs 2 miles of 36" pipe.

Spreads

SpreadDates
Line 28 Loop[7][8]from 1 March 2025

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Cost
  • $368 million (EIA estimate; no dollar year given)[2]
  • $368,729,684 estimated total cost of the projects (certificate order)[5]

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Appalachia to Market II & Armagh & Entriken HP Replacement Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC eLibrary docket CP22-486”. Federal Energy Regulatory Commission. 7 July 2022. Retrieved 3 October 2026.
  2. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  3. “Biweekly Status Report No. 67 (Aug 22 to Sep 4, 2026), Appalachia to Market II and Armagh and Entriken HP Replacement Projects (CP22-486)”. Texas Eastern Transmission, LP (filed with FERC). 22 September 2026. Retrieved 3 October 2026.
  4. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  5. “Order Issuing Certificate and Approving Abandonment, Appalachia to Market II and Armagh and Entriken HP Replacement Projects (CP22-486)”. Federal Energy Regulatory Commission. 23 October 2023. Retrieved 3 October 2026.
  6. “Biweekly Status Report No. 2 (Feb 23 to Mar 8, 2024), Appalachia to Market II and Armagh and Entriken HP Replacement Projects (CP22-486)”. Texas Eastern Transmission, LP (filed with FERC). 14 March 2024. Retrieved 3 October 2026.
  7. “Implementation Plan and Request for Notice to Proceed, Appalachia to Market II and Armagh and Entriken HP Replacement Projects (CP22-486)”. Texas Eastern Transmission, LP (filed with FERC). 31 October 2023. Retrieved 3 October 2026.
  8. “Biweekly Status Report No. 29 (Mar 8 to Mar 21, 2025), Appalachia to Market II and Armagh and Entriken HP Replacement Projects (CP22-486)”. Texas Eastern Transmission, LP (filed with FERC). 31 March 2025. Retrieved 3 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.