Bessemer Calera Expansion Project is a natural gas pipeline expansion in Alabama. Construction began in 2024 and the line entered service in 2025. It runs 4.1 miles of 4", 12" pipe.
| Bessemer Calera Expansion Project | |
|---|---|
| General information | |
| Kind | Pipeline project[1] |
| Project type | Expansion[1][2] |
| Status | In service[3] |
| Commodity | Natural gas[4] |
| Owners and operators | |
| State | Alabama[4] |
| Counties | Jefferson, Perry, Shelby[4] |
| Construction started | 18 March 2024[6] |
| In service | 2025[3] |
| FERC dockets | CP24-32[5], CP24-470[2], CP25-6[1] |
| Technical information | |
| Length | 4.1 mi[4] |
| Pipe size | 4", 12"[4] |
| Cost | $25,000,000 (cost stated in FERC staff EA)[4] |
| On ProvenHand | |
| Hands listed | 0 |
Bessemer Calera Expansion Project is a natural gas pipeline expansion in Alabama. Construction began in 2024 and the line entered service in 2025. It runs 4.1 miles of 4", 12" pipe.
Sources disagree
These sources give different values for the same fact. Each value is listed with the sources that give it.
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Bessemer Calera Expansion Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “FERC eLibrary docket CP25-6”. Federal Energy Regulatory Commission. 15 October 2024. Retrieved 3 October 2026.
- “FERC eLibrary docket CP24-470”. Federal Energy Regulatory Commission. 24 May 2024. Retrieved 3 October 2026.
- “Weekly Status Report No. 46 (January 28 to February 4, 2025), Bessemer Calera Expansion Project (CP24-32 and CP25-6)”. Southern Natural Gas Company, L.L.C. (filed with FERC). 19 February 2025. Retrieved 3 October 2026.
- “Environmental Assessment Report, Bessemer Calera Expansion Project (CP24-32)”. FERC. 29 February 2024. Retrieved 3 October 2026.
- “FERC eLibrary docket CP24-32”. Federal Energy Regulatory Commission. 21 December 2023. Retrieved 3 October 2026.
- “Weekly Environmental Status Report No. 1 (March 18 to 22, 2024), Bessemer Calera Expansion Project (CP24-32)”. Southern Natural Gas Company, L.L.C. (filed with FERC). 25 March 2024. Retrieved 3 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.