Blackwell Redundant Compression Project is a natural gas facility project in Oklahoma, operated by Southern Star Central Gas Pipeline, Inc.. Construction began in 2019.

Blackwell Redundant Compression Project
General information
KindFacility project[1]
Project typeAdded units[2]
StatusIn service[3]
CommodityNatural gas[4]
Owner and operator
StateOklahoma[2]
CountiesKay[2]
Construction started4 February 2019[5]
FERC docketCP19-18[1]
Contractors
Technical information
Units added1 (gas-fired, 4,760 hp each)[2]
Horsepower added4,760 hp[2]
Cost$28,496,850 (cost stated in FERC staff EA)[4]
On ProvenHand
Hands listed0

Blackwell Redundant Compression Project is a natural gas facility project in Oklahoma, operated by Southern Star Central Gas Pipeline, Inc.. Construction began in 2019.

Contractorsedit

ContractorWorkPrime or subScope
Progressive Pipeline Inc.[6]PrimeNamed as the contractor welding, hydrotesting and tying in at the Blackwell compressor station in the weekly environmental inspector reports
Delta Daylighting[7]Hydro-excavation (potholing)Under Progressive Pipeline Inc.Hydrovac potholing crew brought on site by Progressive
Ardent Electric[8]Electrical and instrumentationElectrical conduit, tubing and wiring work at the station, per the weekly environmental inspector reports

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Blackwell Redundant Compression Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC eLibrary docket CP19-18”. Federal Energy Regulatory Commission. 15 November 2018. Retrieved 3 October 2026.
  2. “Prior Notice Request, Blackwell Redundant Compression Project (CP19-18)”. Southern Star Central Gas Pipeline, Inc. (filed with FERC). 15 November 2018. Retrieved 3 October 2026.
  3. “Final Environmental Inspector's Weekly Report No. 29 (period ending August 24, 2019), Blackwell Redundant Compression Project (CP19-18)”. Southern Star Central Gas Pipeline, Inc. (filed with FERC). 28 August 2019. Retrieved 3 October 2026.
  4. “Environmental Assessment Report, Blackwell Redundant Compression Project (CP19-18)”. FERC. 24 January 2019. Retrieved 3 October 2026.
  5. “Environmental Inspector's Weekly Report No. 1 (February 3 to 9, 2019), Blackwell Redundant Compression Project (CP19-18)”. Southern Star Central Gas Pipeline, Inc. (filed with FERC). 19 February 2019. Retrieved 3 October 2026.
  6. “Environmental Inspector's Weekly Report (June 23 to 29, 2019), Blackwell Redundant Compression Project (CP19-18)”. Southern Star Central Gas Pipeline, Inc. (filed with FERC). 2 July 2019. Retrieved 3 October 2026.
  7. “Environmental Inspector's Weekly Report (March 3 to 9, 2019), Blackwell Redundant Compression Project (CP19-18)”. Southern Star Central Gas Pipeline, Inc. (filed with FERC). 13 March 2019. Retrieved 3 October 2026.
  8. “Environmental Inspector's Weekly Report No. 26 (July 28 to August 3, 2019), Blackwell Redundant Compression Project (CP19-18)”. Southern Star Central Gas Pipeline, Inc. (filed with FERC). 7 August 2019. Retrieved 3 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.