Bluewater Compressor Project is a natural gas pipeline expansion in Michigan, operated by Bluewater Gas Storage.

Bluewater Compressor Project
General information
KindPipeline project[1]
Project typeExpansion[1]
StatusIn service[1][2]
CommodityNatural gas[1]
Operator
Owner and operator
StateMichigan[1]
CountiesMacomb[4]
Approved21 May 2020[4]
In service19 November 2021[1] or 1 November 2021[2][sources disagree]
FERC docketCP19-471[1]
Technical information
Capacity380 MMcf/d additional capacity (EIA)[1]
Cost$40 million (EIA estimate; no dollar year given)[1][4]
On ProvenHand
Hands listed0

Bluewater Compressor Project is a natural gas pipeline expansion in Michigan, operated by Bluewater Gas Storage.

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
In service
  • 19 November 2021[1]
  • 1 November 2021[2]

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Bluewater Compressor Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  2. “Notice of Commencement of Service, Bluewater Compression Project (CP19-471)”. Bluewater Gas Storage, LLC (filed with FERC). 10 November 2021. Retrieved 4 October 2026.
  3. “FERC eLibrary docket CP19-471”. Federal Energy Regulatory Commission. 23 May 2019. Retrieved 3 October 2026.
  4. “Order Issuing Certificate, Bluewater Gas Storage, LLC (CP19-471)”. Federal Energy Regulatory Commission. 21 May 2020. Retrieved 4 October 2026.