Carty Lateral Project

From the ProvenHand pipeline wiki

Sources disagree on some of this page's facts. Each value is shown with its sources; see Sources disagree.

Carty Lateral Project is a natural gas pipeline lateral in Oregon, operated by Gas Transmission Northwest LLC. Construction began in 2015.

Carty Lateral Project
General information
KindPipeline project[1]
Project typeLateral[2]
StatusIn service[2]
CommodityNatural gas[2]
Owner and operator
StateOregon[1][2]
Approved14 March 2013[1]
Construction started14 May 2015[3]
In service4 November 2015[2] or 26 October 2015[4][sources disagree]
FERC docketCP12-494[1]
FERC pre-filing docketPF11-5[1]
Technical information
Length24.3 mi[1] or 24.4 mi[2][sources disagree]
Pipe size20"[2]
Capacity175 MMcf/d (FERC project list)[1][2]
Cost$54.3 million (EIA estimate; no dollar year given)[2] or $56,820 thousand total cost of facilities (actual)[5][sources disagree]
On ProvenHand
Hands listed0

Carty Lateral Project is a natural gas pipeline lateral in Oregon, operated by Gas Transmission Northwest LLC. Construction began in 2015.

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Cost
  • $54.3 million (EIA estimate; no dollar year given)[2]
  • $56,820 thousand total cost of facilities (actual)[5]
In service
  • 4 November 2015[2]
  • 26 October 2015[4]
Length

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Carty Lateral Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  2. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  3. “Notice of Commencement of Construction, Carty Lateral Project (CP12-494)”. Gas Transmission Northwest LLC (filed with FERC). 20 May 2015. Retrieved 4 October 2026.
  4. “Notice of Commencement of Service, Carty Lateral Project (CP12-494)”. Gas Transmission Northwest LLC (filed with FERC). 4 November 2015. Retrieved 4 October 2026.
  5. “Carty Lateral Project Cost Comparison Report (CP12-494)”. Gas Transmission Northwest LLC (filed with FERC). 6 April 2016. Retrieved 4 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.