CEGT Searcy Ph 2

From the ProvenHand pipeline wiki

Sources disagree on some of this page's facts. Each value is shown with its sources; see Sources disagree.

CEGT Searcy Ph 2 is a natural gas pipeline in Arkansas, operated by Centerpoint Energy Gas Transmission. It was built and entered service in 2009.

CEGT Searcy Ph 2
Also calledSearcy Phase II Project[1]
General information
KindPipeline project[2] or Facility project[1][sources disagree]
Project typeLateral[2] or Added units[1][sources disagree]
StatusIn service[2]
CommodityNatural gas[1][2]
Operator
Owner and operator
StateArkansas[1][2]
CountiesWhite[1]
Construction started30 August 2009[4]
In service25 May 2009[2]
FERC docketCP09-175[2]
Technical information
Capacity250 MMcf/d additional capacity (EIA)[2]
Capacity addedinterconnect capacity from 125,000 Dth/d to 250,000 Dth/d[1][5]
Units added1 (2,370 hp each)[1]
Horsepower added2,370 hp[1][5]
Cost$10 million (EIA estimate; no dollar year given)[2] or $9.9 million[1][5][sources disagree]
On ProvenHand
Hands listed0

CEGT Searcy Ph 2 is a natural gas pipeline in Arkansas, operated by Centerpoint Energy Gas Transmission. It was built and entered service in 2009.

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Project type
Cost
  • $10 million (EIA estimate; no dollar year given)[2]
  • $9.9 million[1][5]
Kind
  • Pipeline project[2]
  • Facility project[1]

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on CEGT Searcy Ph 2? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “Notice of request under blanket authorization, CenterPoint Energy Gas Transmission Company (CP09-175)”. FERC. 5 May 2009. Retrieved 4 October 2026.
  2. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  3. “FERC eLibrary docket CP09-175”. Federal Energy Regulatory Commission. 24 April 2009. Retrieved 3 October 2026.
  4. “Environmental Inspector's weekly report for the period ending 12/06/09, Searcy Phase II Project, CenterPoint Energy Gas Transmission Company (CP09-175)”. CenterPoint Energy Gas Transmission Company (filed with FERC). 7 December 2009. Retrieved 4 October 2026.
  5. “Environmental Assessment Report, Searcy Phase II (CP09-175)”. FERC. 18 June 2009. Retrieved 4 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.