CGT Cobb Expansion Project is a natural gas pipeline expansion in West Virginia, operated by NiSource Gas Transmission & Storage. It entered service in 2010.
| CGT Cobb Expansion Project | |
|---|---|
| Also called | Cobb Expansion Project[1] |
| General information | |
| Kind | Pipeline project[2] |
| Project type | Expansion[2][3] |
| Status | In service[1][2] |
| Commodity | Natural gas[2] |
| Operator | |
| Owner and operator | |
| Facility project | |
| State | West Virginia[2][4] |
| Counties | Kanawha[4] |
| In service | 17 May 2010[1][2] |
| FERC docket | CP09-437[2] |
| Technical information | |
| Length | 1 mi[2] or 0.7 mi[4][sources disagree] |
| Pipe size | 16"[2][4][5] |
| Capacity | 27.6 MMcf/d additional capacity (EIA)[2] |
| Units added | 1 (electric motor, 4,500 hp each)[5] |
| Horsepower added | 4,500 hp[4] |
| Cost | $16.1 million (EIA estimate; no dollar year given)[2][4][5] |
| On ProvenHand | |
| Hands listed | 0 |
CGT Cobb Expansion Project is a natural gas pipeline expansion in West Virginia, operated by NiSource Gas Transmission & Storage. It entered service in 2010.
Sources disagree
These sources give different values for the same fact. Each value is listed with the sources that give it.
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on CGT Cobb Expansion Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “In-service noise report, Cobb Expansion Project, Columbia Gas Transmission, LLC (CP09-437)”. Columbia Gas Transmission, LLC (filed with FERC). 20 July 2010. Retrieved 4 October 2026.
- “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
- “FERC eLibrary docket CP09-437”. Federal Energy Regulatory Commission. 19 June 2009. Retrieved 3 October 2026.
- “Notice of request under blanket authorization, Columbia Gas Transmission, LLC (CP09-437)”. FERC. 2 July 2009. Retrieved 4 October 2026.
- “Environmental Assessment Report, Cobb Expansion Project (CP09-437)”. FERC. 29 September 2009. Retrieved 4 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.