Cheyenne Connector Pipeline is a natural gas pipeline expansion in Colorado, operated by Tallgrass Energy. Construction began in 2019 and the line entered service in 2020. It runs 70 miles of 36" pipe.[1]

Cheyenne Connector Pipeline
Also calledCheyenne Connector
General information
Project typeExpansion[3]
StatusIn service[3]
CommodityNatural gas[3]
OperatorTallgrass Energy
Operator
Owner and operator
StateColorado[3][5]
CountiesWeld[5]
Approved20 September 2019[6][7]
Construction started2019
In service24 June 2020[3]
FERC docketCP18-102[6]
Contractors
Technical information
Length70 mi[3][5]
Pipe size36"[3][5]
Capacity600 MMcf/d additional capacity (EIA)[3]
Cost$213 million (EIA estimate; no dollar year given)[3]
On ProvenHand
Hands listed0

Cheyenne Connector Pipeline is a natural gas pipeline expansion in Colorado, operated by Tallgrass Energy. Construction began in 2019 and the line entered service in 2020. It runs 70 miles of 36" pipe.[1]

Contractorsedit

ContractorWorkScopeYears
Hanging H Companies, LLC[8]PrimeMainline construction of 72 miles of 36-inch pipe: clearing, stringing, welding, coating, lowering-in, restoration (firm's figures)until 1 January 2020
Lunda Construction Company[9]Temporary sheet pile and shoringTemporary deep sheet pile bore boxes under municipal water drainage structures for the 36-inch pipe (Weld County, CO)until 1 January 2020

Pipe mills

MillDiameterGrade
Borusan Berg Pipe[10]36 inX70

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Cheyenne Connector Pipeline? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. sec.gov · tge2019123110k.htm
  2. sec.gov · dpm-20201231.htm
  3. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  4. “FERC eLibrary docket CP18-102”. Federal Energy Regulatory Commission. 5 March 2018. Retrieved 3 October 2026.
  5. “Notice of Application, Cheyenne Connector, LLC (CP18-102)”. FERC (public notice, eLibrary). 19 March 2018. Retrieved 4 October 2026.
  6. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  7. “Order Issuing Certificates, Cheyenne Connector, LLC et al. (CP18-102 et al.)”. FERC (eLibrary filing description). 20 September 2019. Retrieved 4 October 2026.
  8. “Cheyenne Connector (portfolio page)”. Hanging H Companies, LLC. Archived from the original on 10 April 2021. Retrieved 3 October 2026.
  9. “Cheyenne Connector Pipeline Project”. Lunda Construction Company. Retrieved 3 October 2026.
  10. “Borusan Berg Pipe - Selected Projects”. Borusan Berg Pipe. Retrieved 3 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.