Columbia Gas Transmission Line R300 Replacement Project

From the ProvenHand pipeline wiki

Columbia Gas Transmission Line R300 Replacement Project is a natural gas pipeline replacement in Ohio, operated by Columbia Gas Transmission, LLC. It was built and entered service in 2023. It runs 1.2 miles of 18" pipe.

Columbia Gas Transmission Line R300 Replacement Project
General information
KindPipeline project[1]
Project typeReplacement[1]
StatusIn service[2]
CommodityNatural gas[3]
Owner and operator
StateOhio[3]
CountiesLawrence[3]
Construction startedMarch 2023[4]
In service30 June 2023[2]
FERC docketCP23-13[1]
Technical information
Length1.2 mi[3]
Pipe size18"[3]
Costapproximately $3,700,000[3]
On ProvenHand
Hands listed0

Columbia Gas Transmission Line R300 Replacement Project is a natural gas pipeline replacement in Ohio, operated by Columbia Gas Transmission, LLC. It was built and entered service in 2023. It runs 1.2 miles of 18" pipe.

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Columbia Gas Transmission Line R300 Replacement Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC eLibrary docket CP23-13”. Federal Energy Regulatory Commission. 7 November 2022. Retrieved 3 October 2026.
  2. “Weekly Construction Status Report No. 19 (last), Line R300 Replacement Project (CP23-13)”. Columbia Gas Transmission, LLC (filed with FERC). 11 August 2023. Retrieved 4 October 2026.
  3. “Notice of Request Under Blanket Authorization, Columbia Gas Transmission, LLC (CP23-13)”. Federal Energy Regulatory Commission. 17 November 2022. Retrieved 4 October 2026.
  4. “Weekly Construction Status Report No. 1, Line R300 Replacement Project (CP23-13)”. Columbia Gas Transmission, LLC (filed with FERC). 6 April 2023. Retrieved 4 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.