Columbia Gas Transmission Rock Springs Expansion is a natural gas pipeline lateral, operated by Columbia Gas Transmission, LLC. It entered service in 2003.

Columbia Gas Transmission Rock Springs Expansion
Also calledCGT Rock Springs Expansion[1]
General information
KindPipeline project[1]
Project typeLateral[2]
StatusIn service[2]
CommodityNatural gas[2]
Owner and operator
StatePA[1] or MD, PA[2][sources disagree]
Approved20 December 2002[1]
In service10 December 2003[2]
FERC docketCP02-142[1]
Technical information
Length9.1 mi[1] or 9.3 mi[2][sources disagree]
Pipe size10", 24"[2]
Capacity270 MMcf/d (FERC project list)[1] or 263 MMcf/d additional capacity (EIA)[2][sources disagree]
Cost$29.2 million (EIA estimate; no dollar year given)[2]
On ProvenHand
Hands listed0

Columbia Gas Transmission Rock Springs Expansion is a natural gas pipeline lateral, operated by Columbia Gas Transmission, LLC. It entered service in 2003.

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Capacity
  • 270 MMcf/d (FERC project list)[1]
  • 263 MMcf/d additional capacity (EIA)[2]
Length
States

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Columbia Gas Transmission Rock Springs Expansion? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  2. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.