As contractor

ProjectWorkPrime or subScopeProject built
Albert Lea North E-line Expansion Project[1]HDD and boreUnder Otis Minnesota ServicesDrilled the two HDD crossings (P4-1 and P4-2) of the 36-inch E-line extension2023
10" North System Pipeline Relocation - Cass County[2]HDD and bore2021

Crossings

Crossings this company drilled or bored.

ProjectFeatureDates
Albert Lea North E-line Expansion ProjectWaterbody ALO-S01 (unnamed perennial stream), HDD P4-1[4][5]28 June 2023 – 2 August 2023
Albert Lea North E-line Expansion ProjectWaterbody ALO-S02 (unnamed perennial stream), HDD P4-2[4][5]28 June 2023 – 28 July 2023

References

  1. “Weekly Environmental Inspector Report No. 5 (June 19 to June 25, 2023), Albert Lea North E-line Expansion Project (CP22-489)”. Northern Natural Gas Company (filed with FERC). 28 June 2023. Retrieved 3 October 2026.
  2. “NuStar Pipeline, 10" North System Pipeline Relocation, progress report, June 2021, case PU-20-381, docket 58”. NuStar Pipeline Operating Partnership L.P. (filed with the North Dakota Public Service Commission). 29 June 2021. Retrieved 3 October 2026.
  3. “PLCA Member Directory”. Pipe Line Contractors Association. Retrieved 3 October 2026.
  4. “Environmental Report for Prior Notice (Attachment E), Albert Lea North E-Line Expansion Project (CP22-489)”. Northern Natural Gas Company (filed with FERC). 15 July 2022. Retrieved 3 October 2026.
  5. “Weekly Environmental Inspector Report No. 11 (July 31 to August 6, 2023), Albert Lea North E-line Expansion Project (CP22-489)”. Northern Natural Gas Company (filed with FERC). 10 August 2023. Retrieved 3 October 2026.