Rooney Engineering, Inc.
From the ProvenHand pipeline wiki
Rooney Engineering, Inc. is a pipeline contractor.
| Rooney Engineering, Inc. | |
|---|---|
| General information | |
| Industry | |
| PLCA | Not a PLCA member as of 3 October 2026[4] |
| On ProvenHand | |
| Hands listed | 0 |
Rooney Engineering, Inc. is a pipeline contractor.
This company article is a stub. You can help ProvenHand by expanding it.
Projects
As contractor
| Project | Work | Project built |
|---|---|---|
| Stanley & Beaver Lodge - Mountrail & Williams Cty[1] | engineering and supervising project management (author of the weekly construction progress reports) | 2011–2012 |
| Berthold Station Line Reversal - Ward County[2] | engineering and supervising project management (author of the weekly construction progress reports) | |
| Stanley Pump Station Construction[3] | engineering and supervising project management (author of the weekly construction progress reports) |
References
- “Beaver Lodge project weekly construction progress report, week of June 25 to 29, 2012, PU-11-327”. Enbridge Pipelines (North Dakota) LLC (filed with the North Dakota Public Service Commission). 28 June 2012. Retrieved 3 October 2026.
- “Berthold Station final progress report, PU-10-564 / PU-10-130”. Enbridge Pipelines (North Dakota) LLC (filed with the North Dakota Public Service Commission). 13 June 2012. Retrieved 3 October 2026.
- “Stanley Tank Project weekly final progress report (email from Rooney Engineering, 2010-12-17), PU-10-33”. Enbridge Pipelines (North Dakota) LLC (filed with the North Dakota Public Service Commission). 21 December 2010. Retrieved 3 October 2026.