Cumberland Project
From the ProvenHand pipeline wiki
Cumberland Project is a natural gas pipeline lateral in Tennessee, operated by Tennessee Gas Pipeline Company, L.L.C.. Construction began in 2024 and the line entered service in 2026. It runs 32 miles of 30" pipe.
| Cumberland Project | |
|---|---|
| General information | |
| Kind | Pipeline project[1] |
| Project type | Lateral[1][2] |
| Status | In service[1][3] |
| Commodity | Natural gas[1] |
| Operator | |
| Owner and operator | |
| State | Tennessee[1][2] |
| Counties | Dickson, Houston, Stewart[2] |
| Approved | 18 January 2024[2] |
| Construction started | 2024[6] |
| In service | 26 May 2026[1][3] |
| FERC docket | CP22-493[1] |
| FERC pre-filing docket | PF22-2[5] |
| Technical information | |
| Length | 32 mi[1][2] |
| Pipe size | 30"[1][2] |
| Wall thickness | 0.375, 0.5 and 0.625 in[7] |
| Grades | X65, X70[7] |
| Mill coating | FBE 14-16 mils; ARO 30-40 mils at bored crossings[8] |
| Capacity | 245 MMcf/d additional capacity (EIA)[1] |
| Cost | $235 million (Kinder Morgan Q2 2026 update, via P&GJ)[9] or $184.8 million estimate incl. contingency, overheads and AFUDC (2022 application)[10][sources disagree] |
| On ProvenHand | |
| Hands listed | 0 |
Cumberland Project is a natural gas pipeline lateral in Tennessee, operated by Tennessee Gas Pipeline Company, L.L.C.. Construction began in 2024 and the line entered service in 2026. It runs 32 miles of 30" pipe.
Inspection
| Firm | Scope | Years |
|---|---|---|
| Burns & McDonnell Engineering[11] | Third-party FERC environmental compliance monitoring program (compliance manager and monitor) | from 1 April 2025 |
Spreads
| Spread | Dates |
|---|---|
| Cumberland Pipeline mainline[12] | from 1 April 2025 |
Crossings
| Feature | Method |
|---|---|
| Jones Creek (MP 3.2)[7][8] | HDD |
| Wells Creek (MP 30.7)[7][8] | HDD |
| Yellow Creek and an unnamed tributary (MP 22.4)[7][8] | HDD |
Sources disagree
These sources give different values for the same fact. Each value is listed with the sources that give it.
| Fact | Values given |
|---|---|
| Cost |
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Cumberland Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
- “Order Issuing Certificate, Tennessee Gas Pipeline Company, L.L.C., Cumberland Project (CP22-493)”. Federal Energy Regulatory Commission. 18 January 2024. Retrieved 3 October 2026.
- “Notification of Placing Project Facilities In-Service, Cumberland Project (CP22-493)”. Tennessee Gas Pipeline Company, L.L.C. (filed with FERC). 3 June 2026. Retrieved 3 October 2026.
- “FERC eLibrary docket CP22-493”. Federal Energy Regulatory Commission. 22 July 2022. Retrieved 3 October 2026.
- “FERC eLibrary docket PF22-2”. Federal Energy Regulatory Commission. 29 October 2021. Retrieved 3 October 2026.
- “Weekly Status Report, September 29 to October 5, 2024, Cumberland Project (CP22-493)”. Tennessee Gas Pipeline Company, L.L.C. (filed with FERC). 9 October 2024. Retrieved 3 October 2026.
- “Implementation Plan, Cumberland Project (CP22-493)”. Tennessee Gas Pipeline Company, L.L.C. (filed with FERC). 12 April 2024. Retrieved 3 October 2026.
- “Final Environmental Impact Statement, Cumberland Project (CP22-493)”. Federal Energy Regulatory Commission. 30 June 2023. Retrieved 3 October 2026.
- “Kinder Morgan Raises 2026 Outlook as Gas Project Backlog Tops $9.6 Billion”. Pipeline & Gas Journal. 23 July 2026. Retrieved 3 October 2026.
- “Application for a Certificate of Public Convenience and Necessity, Cumberland Project (CP22-493)”. Tennessee Gas Pipeline Company, L.L.C. (filed with FERC). 22 July 2022. Retrieved 3 October 2026.
- “Environmental Compliance Monitoring Program Work Plan, Cumberland Project (CP22-493)”. Tennessee Gas Pipeline Company, L.L.C. (filed with FERC). 23 April 2025. Retrieved 3 October 2026.
- “Weekly Status Report, April 21 to 27, 2025, Cumberland Project (CP22-493)”. Tennessee Gas Pipeline Company, L.L.C. (filed with FERC). 30 April 2025. Retrieved 3 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.