Dowell Hill Replacement Project is a natural gas pipeline replacement in Indiana, operated by ANR Pipeline Company. It was built and entered service in 2024. It runs 1.4 miles of 30" pipe.

Dowell Hill Replacement Project
General information
KindPipeline project[1]
Project typeReplacement[1]
StatusIn service[2]
CommodityNatural gas[3]
Owner and operator
StateIndiana[3]
CountiesBartholomew[3]
Construction startedMarch 2024[4]
In service25 November 2024[2]
FERC docketCP24-24[1]
Technical information
Length1.4 mi[3]
Pipe size30"[3]
Cost$25,000,000 (cost stated in FERC staff EA)[3]
On ProvenHand
Hands listed0

Dowell Hill Replacement Project is a natural gas pipeline replacement in Indiana, operated by ANR Pipeline Company. It was built and entered service in 2024. It runs 1.4 miles of 30" pipe.

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Dowell Hill Replacement Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC eLibrary docket CP24-24”. Federal Energy Regulatory Commission. 12 December 2023. Retrieved 3 October 2026.
  2. “Weekly Construction Status Report No. 40 (December 8 to 14, 2024), Dowell Hill Replacement Project (CP24-24)”. ANR Pipeline Company (filed with FERC). 17 December 2024. Retrieved 3 October 2026.
  3. “Environmental Assessment Report, Dowell Hill Replacement Project (CP24-24)”. FERC. 16 February 2024. Retrieved 3 October 2026.
  4. “Weekly Construction Status Report No. 1 (March 10 to 16, 2024), Dowell Hill Replacement Project (CP24-24)”. ANR Pipeline Company (filed with FERC). 18 March 2024. Retrieved 3 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.