Driftwood Pipeline Line 200 and Line 300 Project is a natural gas pipeline in Louisiana, operated by Driftwood Pipeline LLC. Construction began in 2026.
| Driftwood Pipeline Line 200 and Line 300 Project | |
|---|---|
| General information | |
| Kind | Pipeline project[1] |
| Project type | New build[2] |
| Status | Under construction[3] |
| Commodity | Natural gas[2] |
| Owner and operator | |
| Facility project | |
| State | Louisiana[1] |
| Counties | Beauregard, Calcasieu[2] |
| Approved | 21 April 2023[1][2] |
| Construction started | September 2026[3] |
| FERC docket | CP21-465[1] |
| Contractors | |
| Technical information | |
| Pipe size | 42"[2] |
| Capacity | 1100 MMcf/d (FERC project list)[1] or up to 5,400,000 Dth/d firm transportation[2][sources disagree] |
| Cost | approximately $1,525,405,257[2] |
| On ProvenHand | |
| Hands listed | 0 |
Driftwood Pipeline Line 200 and Line 300 Project is a natural gas pipeline in Louisiana, operated by Driftwood Pipeline LLC. Construction began in 2026.
Contractorsedit
| Contractor | Work | Scope |
|---|---|---|
| Perennial Environmental Services, LLC[4] | Environmental survey consultant (rare plant species surveys) | Rare plant species habitat surveys along the Line 200 and Line 300 route (report dated January 2023, filed with FERC July 2026) |
Sources disagree
These sources give different values for the same fact. Each value is listed with the sources that give it.
| Fact | Values given |
|---|---|
| Capacity |
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Driftwood Pipeline Line 200 and Line 300 Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
- “Order Issuing Certificate, Driftwood Pipeline LLC, Line 200 and Line 300 Project (CP21-465), 183 FERC 61,049”. Federal Energy Regulatory Commission. 21 April 2023. Retrieved 3 October 2026.
- “Bi-Weekly Construction Status Report (9/8/2026 to 9/22/2026), Line 200 and Line 300 Project (CP21-465)”. Driftwood Pipeline LLC (filed with FERC). 28 September 2026. Retrieved 3 October 2026.
- “Supplemental information to the Implementation Plan, with rare plant species survey report, Line 200 and Line 300 Project (CP21-465)”. Driftwood Pipeline LLC (filed with FERC); survey report prepared by Perennial Environmental Services, LLC. 30 July 2026. Retrieved 3 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.