Frametown Compressor Station Replacement
From the ProvenHand pipeline wiki
Frametown Compressor Station Replacement is a facility project in West Virginia, operated by Columbia Gas Transmission, LLC.
| Frametown Compressor Station Replacement | |
|---|---|
| General information | |
| Kind | Facility project[1] |
| Project type | Rebuild[2] |
| Status | Under construction[3] |
| Owner and operator | |
| State | West Virginia[1] |
| Counties | Braxton[1] |
| FERC docket | CP12-522[2] |
| Technical information | |
| Units added | 1 × Solar Mars 100S (14,640 hp each)[4] |
| Cost | $26,000,000[4] |
| On ProvenHand | |
| Hands listed | 0 |
Frametown Compressor Station Replacement is a facility project in West Virginia, operated by Columbia Gas Transmission, LLC.
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Frametown Compressor Station Replacement? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “Advance notification of horsepower replacement (Section 2.55(b)), Frametown Compressor Station Replacement (CP12-522)”. Columbia Gas Transmission, LLC (filed with FERC). 11 September 2012. Retrieved 4 October 2026.
- “FERC eLibrary docket CP12-522”. Federal Energy Regulatory Commission. 11 September 2012. Retrieved 3 October 2026.
- “Supplemental information, Frametown Compressor Station spoil relocation (CP12-522)”. Columbia Gas Transmission, LLC (filed with FERC). 19 February 2013. Retrieved 4 October 2026.
- “Environmental Assessment Report, Frametown Compressor Station Replacement (CP12-522)”. FERC. 10 October 2012. Retrieved 4 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.