GS Carthage to Keatchie Pipeline Loop is a natural gas pipeline in Louisiana and Texas, operated by Gulf South Pipeline Company, LLC. It entered service in 2006. It runs 20.5 miles of 42" pipe.

GS Carthage to Keatchie Pipeline Loop
Also calledCarthage to Keatchie Pipeline Loop Project[1]
General information
KindPipeline project[2]
Project typeExpansion[2] or Loop[1][3][sources disagree]
StatusIn service[2]
CommodityNatural gas[2]
Owner and operator
StatesLouisiana, Texas[2]
CountiesLouisiana: DeSoto
Texas: Panola
[3]
In service15 December 2006[2]
FERC docketCP06-127[2]
Technical information
Length20.5 mi[2][3]
Pipe size42"[2][3]
Capacity122.4 MMcf/d additional capacity (EIA)[2]
Capacity addedapproximately 112,400 Dth per day of new pipeline capacity[4]
Cost$47.9 million (EIA estimate; no dollar year given)[2]
On ProvenHand
Hands listed0

GS Carthage to Keatchie Pipeline Loop is a natural gas pipeline in Louisiana and Texas, operated by Gulf South Pipeline Company, LLC. It entered service in 2006. It runs 20.5 miles of 42" pipe.

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Project type

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on GS Carthage to Keatchie Pipeline Loop? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC eLibrary docket CP06-127”. Federal Energy Regulatory Commission. 14 April 2006. Retrieved 3 October 2026.
  2. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  3. “Notice of Request Under Blanket Authorization, Gulf South Pipeline Company, LP (CP06-127)”. Federal Energy Regulatory Commission (notice). 25 April 2006. Retrieved 4 October 2026.
  4. “Staff notice withdrawing its protest to the Gulf South Pipeline prior notice request (CP06-127)”. Federal Energy Regulatory Commission (staff filing). 23 June 2006. Retrieved 4 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.