Hawkeye NGL Pipeline - McKenzie&Williams is an NGL pipeline conversion in North Dakota, operated by Hess North Dakota Pipelines LLC. It runs 19.2 miles of 8", 10" pipe.

Hawkeye NGL Pipeline - McKenzie&Williams
Also calledHawkeye NGL Pipeline[1]
General information
KindPipeline project[2]
Project typeConversion[1]
StatusIn service[3]
CommodityNGL[1]
Owner and operator
StateNorth Dakota[2]
CountiesMcKenzie, Williams[1]
Approved22 June 2015[1]
North Dakota PSC casePU-15-032[2]
Contractors
Technical information
Length19.2 mi[1]
Pipe size8", 10"[1]
Capacitycapacity to ship 30,000 barrels of liquid per day at maximum operating pressure[1]
Costinvested amount not determinable; Hess estimated the replacement cost for the line at $37 million[1]
On ProvenHand
Hands listed0

Hawkeye NGL Pipeline - McKenzie&Williams is an NGL pipeline conversion in North Dakota, operated by Hess North Dakota Pipelines LLC. It runs 19.2 miles of 8", 10" pipe.

Contractorsedit

ContractorWork
Stantec[3]environmental consulting (post-construction tree and shrub inventory; commissioned by Hess)

Inspection

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Hawkeye NGL Pipeline - McKenzie&Williams? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “Findings of Fact, Conclusions of Law and Order, Case No. PU-15-32 (Hess Hawkeye NGL Pipeline)”. North Dakota Public Service Commission. 22 June 2015. Retrieved 3 October 2026.
  2. “North Dakota Public Service Commission: case search (pipeline siting)”. North Dakota Public Service Commission. Retrieved 3 October 2026.
  3. “Final Inspection Report, Hess Hawkeye Crude and NGL Pipeline Projects (PU-15-31 and PU-15-32)”. E3 Environmental, LLC (filed with the North Dakota Public Service Commission). 21 August 2017. Retrieved 3 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.