Hillsborough County Project is a pipeline loop, operated by Florida Gas Transmission Company, LLC. It was built and entered service in 2025. It runs 0.9 miles of 8" pipe.

Hillsborough County Project
General information
KindPipeline project[1]
Project typeLoop[2]
StatusIn service[3]
Owner and operator
CountiesHillsborough[2]
Construction started16 September 2025[4]
In service20 November 2025[3]
FERC docketCP25-39[1]
Technical information
Length0.9 mi[2]
Pipe size8"[2]
Cost$10.9M[2]
On ProvenHand
Hands listed0

Hillsborough County Project is a pipeline loop, operated by Florida Gas Transmission Company, LLC. It was built and entered service in 2025. It runs 0.9 miles of 8" pipe.

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Hillsborough County Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC eLibrary docket CP25-39”. Federal Energy Regulatory Commission. 26 December 2024. Retrieved 3 October 2026.
  2. “Environmental Assessment Report for Florida Gas Transmission Company, LLC's Prior Notice Sections 157.205(b), 157.208(c), and 157.211 under CP25-39.”. Federal Energy Regulatory Commission (staff document). 4 March 2025. Retrieved 3 October 2026.
  3. “Florida Gas Transmission Company, LLC submits Weekly Environmental Status Report No. 17 for the period of 01/04/2026 to 01/10/2026 re the Hillsborough County Project under CP25-39.”. Florida Gas Transmission Company, LLC (filed with FERC). 12 January 2026. Retrieved 3 October 2026.
  4. “Florida Gas Transmission Company, LLC submits Weekly Environmental Status Report No. 1 for the period of 09/14/2025 to 09/20/2025 re the Hillsborough County Project under CP25-39.”. Florida Gas Transmission Company, LLC (filed with FERC). 24 September 2025. Retrieved 3 October 2026.