Index 130 MS River Replacement Project
From the ProvenHand pipeline wiki
Index 130 MS River Replacement Project is a natural gas pipeline replacement in Louisiana, operated by Gulf South Pipeline Company, LLC. Construction began in 2026. It runs 1.1 miles of 6", 30" pipe.
| Index 130 MS River Replacement Project | |
|---|---|
| General information | |
| Kind | Pipeline project[1] |
| Project type | Replacement[1] |
| Status | Under construction[2] |
| Commodity | Natural gas[3] |
| Owner and operator | |
| State | Louisiana[3] |
| Counties | Ascension[3] |
| Approved | 18 November 2022[3] |
| Construction started | 7 July 2026[2] |
| FERC docket | CP22-161[1] |
| Technical information | |
| Length | 1.1 mi[3] |
| Pipe size | 6", 30"[3] |
| Cost | approximately $61,206,000[3] |
| On ProvenHand | |
| Hands listed | 0 |
Index 130 MS River Replacement Project is a natural gas pipeline replacement in Louisiana, operated by Gulf South Pipeline Company, LLC. Construction began in 2026. It runs 1.1 miles of 6", 30" pipe.
Crossings
| Feature | Method |
|---|---|
| Mississippi River[3] | HDD |
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Index 130 MS River Replacement Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “FERC eLibrary docket CP22-161”. Federal Energy Regulatory Commission. 8 April 2022. Retrieved 3 October 2026.
- “Monthly Construction/Environmental Status Report for September 2026, Index 130 MS River Replacement Project (CP22-161)”. Gulf South Pipeline Company, LLC (filed with FERC). 1 October 2026. Retrieved 3 October 2026.
- “Order Issuing Certificate and Approving Abandonment, Gulf South Pipeline Company, LLC, Index 130 MS River Replacement Project (CP22-161)”. FERC. 18 November 2022. Retrieved 3 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.