Line Q, QP, and Queen Storage Facility Project
From the ProvenHand pipeline wiki
Line Q, QP, and Queen Storage Facility Project is a natural gas pipeline replacement in Pennsylvania, operated by National Fuel Gas Supply Corporation. Construction began in 2018. It runs 5 miles of 4" pipe.
| Line Q, QP, and Queen Storage Facility Project | |
|---|---|
| General information | |
| Kind | Pipeline project[1] |
| Project type | Replacement[2] |
| Status | In service[3] |
| Commodity | Natural gas[4] |
| Owner and operator | |
| State | Pennsylvania[1] |
| Counties | Forest, Warren[1] |
| Approved | 6 September 2017[4] |
| Construction started | 2018[2] |
| FERC docket | CP16-28[5] |
| Contractors | |
| Technical information | |
| Length | 5 mi[1] |
| Pipe size | 4"[1] |
| On ProvenHand | |
| Hands listed | 0 |
Line Q, QP, and Queen Storage Facility Project is a natural gas pipeline replacement in Pennsylvania, operated by National Fuel Gas Supply Corporation. Construction began in 2018. It runs 5 miles of 4" pipe.
Contractorsedit
| Contractor | Work | Years |
|---|---|---|
| EnviroScience[6] | mussel salvage (approved Mussel Salvage Plan, Allegheny River crossing) | 18 July 2018 – 10 August 2018 |
Inspection
| Firm | Scope |
|---|---|
| Western PA Conservancy[6] | QA/QC of the mussel salvage (completed August 15, 2018) |
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Line Q, QP, and Queen Storage Facility Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “Ongoing Projects: Construction Underway (Pipeline News, July 2018)”. Pipeline News. July 2018. Retrieved 3 October 2026.
- “Post-Construction Wetland Monitoring Report, Line Q Replacement and Abandonment Project (CP16-28)”. National Fuel Gas Supply Corporation (filed with FERC). 9 September 2020. Retrieved 4 October 2026.
- “Letter order authorizing service of the Allegheny River crossing portion, Line Q, QP, and Queen Storage Facility Project (CP16-28)”. Federal Energy Regulatory Commission. 27 September 2018. Retrieved 4 October 2026.
- “Order Issuing Certificate and Approving Abandonment, National Fuel Gas Supply Corporation (CP16-28)”. Federal Energy Regulatory Commission. 6 September 2017. Retrieved 4 October 2026.
- “FERC eLibrary docket CP16-28”. Federal Energy Regulatory Commission. 3 December 2015. Retrieved 3 October 2026.
- “Bi-Weekly Status Report of Construction Activity, 08-20-18 to 09-02-18, Line QP, Line Q and Queen Storage Project (CP16-28)”. National Fuel Gas Supply Corporation (filed with FERC). 10 September 2018. Retrieved 4 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.