Line Section 15 Expansion Project is a natural gas pipeline in South Dakota, operated by WBI Energy Transmission, Inc.. Construction began in 2023.
| Line Section 15 Expansion Project | |
|---|---|
| General information | |
| Kind | Pipeline project[1] |
| Status | In service[2] |
| Commodity | Natural gas[1] |
| Owner and operator | |
| State | South Dakota[1] |
| Counties | Butte, Lawrence, Meade, Pennington[1] |
| Construction started | May 2023[4] |
| FERC docket | CP23-87[3] |
| Technical information | |
| Capacity added | 25,000 dekatherms per day of natural gas[1] |
| Cost | $33,800,000[1] |
| On ProvenHand | |
| Hands listed | 0 |
Line Section 15 Expansion Project is a natural gas pipeline in South Dakota, operated by WBI Energy Transmission, Inc.. Construction began in 2023.
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Line Section 15 Expansion Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “Environmental Assessment Report, WBI Energy Line Section 15 Expansion Project (CP23-87)”. Federal Energy Regulatory Commission (Office of Energy Projects). 15 May 2023. Retrieved 3 October 2026.
- “Weekly Construction Progress Report No. 71 (final, period from 09/16/2024), Line Section 15 Expansion Project (CP23-87)”. WBI Energy Transmission, Inc. (filed with FERC). 27 September 2024. Retrieved 3 October 2026.
- “FERC eLibrary docket CP23-87”. Federal Energy Regulatory Commission. 7 March 2023. Retrieved 3 October 2026.
- “Weekly Construction Progress Report No. 1 (period from May 15, 2023), Line Section 15 Expansion Project (CP23-87)”. WBI Energy Transmission, Inc. (filed with FERC). 26 May 2023. Retrieved 3 October 2026.