Logansport Well Installation Project
From the ProvenHand pipeline wiki
Logansport Well Installation Project is a facility project, operated by Equitrans, L.P..
| Logansport Well Installation Project | |
|---|---|
| Also called | Logansport Storage Injection/Withdrawal Well Replacement Project[1] |
| General information | |
| Kind | Facility project[2] |
| Owner and operator | |
| Counties | Marion[3] |
| FERC docket | CP08-417[2] |
| Technical information | |
| Cost | approximately $4,000,000 (Equitrans estimate)[3] |
| On ProvenHand | |
| Hands listed | 0 |
Logansport Well Installation Project is a facility project, operated by Equitrans, L.P..
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Logansport Well Installation Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “Weekly Status Report for the Logansport Storage Injection/Withdrawal Well Replacement Project, period 9/6/08 to 9/13/08, Equitrans, L.P. (CP08-417)”. Equitrans, L.P. (filed with FERC). 10 October 2008. Retrieved 4 October 2026.
- “FERC eLibrary docket CP08-417”. Federal Energy Regulatory Commission. 2 June 2008. Retrieved 3 October 2026.
- “Equitrans, L.P.; Notice of Request Under Blanket Authorization (Docket No. CP08-417-000), Federal Register E8-13681”. Federal Energy Regulatory Commission (published in the Federal Register). 18 June 2008. Retrieved 4 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.