Mobile Bay South Expansion Project is a natural gas pipeline expansion in Alabama, operated by Transcontinental Gas Pipe Line Company, LLC. It entered service in 2010. It runs 0.5 miles of 30" pipe.

Mobile Bay South Expansion Project
Also calledTransco Mobile Bay South Expansion[1]
General information
KindPipeline project[1]
Project typeExpansion[2][3]
StatusIn service[2]
CommodityNatural gas[2]
Owner and operator
Facility project
StateAlabama[1][2]
CountiesChoctaw[4]
Approved7 May 2009[1]
In serviceMay 2010[2][5]
FERC docketCP08-476[1]
Technical information
Length0.5 mi[1]
Pipe size30"[4]
Capacity253.5 MMcf/d (FERC project list)[1][2]
Cost$36.903 million (EIA estimate; no dollar year given)[2] or approximately $34 million estimated capital cost[5][sources disagree]
On ProvenHand
Hands listed0

Mobile Bay South Expansion Project is a natural gas pipeline expansion in Alabama, operated by Transcontinental Gas Pipe Line Company, LLC. It entered service in 2010. It runs 0.5 miles of 30" pipe.

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Cost
  • $36.903 million (EIA estimate; no dollar year given)[2]
  • approximately $34 million estimated capital cost[5]

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Mobile Bay South Expansion Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  2. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  3. “FERC eLibrary docket CP08-476”. Federal Energy Regulatory Commission. 18 September 2008. Retrieved 3 October 2026.
  4. “Order Issuing Certificate, Transcontinental Gas Pipe Line Corporation, Mobile Bay South Expansion Project (CP08-476)”. Federal Energy Regulatory Commission. 7 May 2009. Retrieved 4 October 2026.
  5. “Transcontinental Gas Pipe Line Company, LLC Form 10-Q for the quarter ended June 30, 2010”. Transcontinental Gas Pipe Line Company, LLC (SEC filing). 29 July 2010. Retrieved 4 October 2026.