Monroe Gas Storage Project
From the ProvenHand pipeline wiki
Monroe Gas Storage Project is a natural gas facility project in Alabama and Mississippi, operated by Monroe Gas Storage Company, LLC. Construction began in 2008.
| Monroe Gas Storage Project | |
|---|---|
| General information | |
| Kind | Facility project[1] |
| Project type | Rebuild[1] |
| Status | In service[2] |
| Commodity | Natural gas[3] |
| Owner and operator | |
| Facility projects | |
| States | Alabama, Mississippi[3] |
| Counties | Alabama: Lamar Mississippi: Monroe[3] |
| Approved | 21 December 2007[3] |
| Construction started | June 2008[7] |
| FERC docket | CP07-406[1] |
| On ProvenHand | |
| Hands listed | 0 |
Monroe Gas Storage Project is a natural gas facility project in Alabama and Mississippi, operated by Monroe Gas Storage Company, LLC. Construction began in 2008.
Inspection
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Monroe Gas Storage Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “FERC eLibrary docket CP07-406”. Federal Energy Regulatory Commission. 26 June 2007. Retrieved 3 October 2026.
- “Letter order approving the 5/15/09 request to place the Monroe Gas Storage Project compressor station facilities into service (CP07-406), eLibrary filing description”. FERC. 26 May 2009. Retrieved 4 October 2026.
- “Request for Written Authorization to Commence Service, Monroe Gas Storage Project (CP07-406)”. Monroe Gas Storage Company, LLC (filed with FERC). 13 March 2009. Retrieved 4 October 2026.
- “Order Amending Certificate, Monroe Gas Storage Company, LLC (CP11-28)”. Federal Energy Regulatory Commission. 3 December 2010. Retrieved 4 October 2026.
- “FERC eLibrary filing 20110425-3013”. Federal Energy Regulatory Commission. Retrieved 4 October 2026.
- “Order Issuing Certificates, Monroe Gas Storage Company, LLC, Docket Nos. CP07-406-000, CP07-407-000 and CP07-408-000”. Federal Energy Regulatory Commission. 21 December 2007. Retrieved 4 October 2026.
- “Bi-Weekly Status Report No. 1, commencement of construction through 06-22-08, Monroe Gas Storage Project (CP07-406)”. Monroe Gas Storage Company, LLC (filed with FERC). 25 June 2008. Retrieved 4 October 2026.
- “Projects, La-Tex Associates”. La-Tex Associates. Retrieved 3 October 2026.