NCPL Sandhills Pipeline Project is a natural gas pipeline in North Carolina, operated by Progress Energy Corp. It entered service in 2001. It runs 84 miles of 30" pipe.

NCPL Sandhills Pipeline Project
General information
KindPipeline project[1]
Project typeNew build[1]
StatusIn service[1]
CommodityNatural gas[1]
Operator
StateNorth Carolina[1]
In serviceMarch 2001[1]
Contractors
Technical information
Length84 mi[1]
Pipe size30"[1]
Capacity300 MMcf/d additional capacity (EIA)[1]
Cost$100 million (EIA estimate; no dollar year given)[1]
On ProvenHand
Hands listed0

NCPL Sandhills Pipeline Project is a natural gas pipeline in North Carolina, operated by Progress Energy Corp. It entered service in 2001. It runs 84 miles of 30" pipe.

Contractorsedit

ContractorWorkScopeYears
U.S. Pipeline, Inc.[2][3]PrimeSandhills Gas Pipeline Project: 83 miles of 30-inch pipeline, Davidson to Hamlet, North Carolinafrom 1 January 2000

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on NCPL Sandhills Pipeline Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  2. “Past Projects (archive 2005-12-27)”. U.S. Pipeline, Inc. Archived from the original on 27 December 2005. Retrieved 3 October 2026.
  3. “USPL Current Construction (archive 2000-10-01)”. U.S. Pipeline, Inc. Archived from the original on 1 October 2000. Retrieved 3 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.