Northeast Connector Project

From the ProvenHand pipeline wiki

Sources disagree on some of this page's facts. Each value is shown with its sources; see Sources disagree.

Northeast Connector Project is a natural gas pipeline expansion, operated by Transcontinental Gas Pipe Line Company, LLC. Construction began in 2014.

Northeast Connector Project
General information
KindPipeline project[1] or Facility project[2][sources disagree]
Project typeExpansion[3]
StatusIn service[3][4]
CommodityNatural gas[3]
Owner and operator
Facility projects
StatesNJ, PA[1] or NJ, NY, PA[3][sources disagree]
CountiesNew Jersey: Mercer, Middlesex
Pennsylvania: York
[2]
Approved8 May 2014[1][2]
Construction started20 May 2014[5]
In service7 November 2014[3] or 1 December 2014[4][sources disagree]
FERC docketCP13-132[1]
Technical information
Capacity100 MMcf/d (FERC project list)[1][3]
Cost$48.5 million (EIA estimate; no dollar year given)[3] or $52,347,416 total actual and forecast cost as of May 2015 (cost report; the estimate was $48,470,009)[6][sources disagree]
On ProvenHand
Hands listed0

Northeast Connector Project is a natural gas pipeline expansion, operated by Transcontinental Gas Pipe Line Company, LLC. Construction began in 2014.

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Cost
  • $48.5 million (EIA estimate; no dollar year given)[3]
  • $52,347,416 total actual and forecast cost as of May 2015 (cost report; the estimate was $48,470,009)[6]
In service
  • 7 November 2014[3]
  • 1 December 2014[4]
Kind
  • Pipeline project[1]
  • Facility project[2]
States

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Northeast Connector Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  2. “Order Issuing Certificates and Granting Abandonment, Transcontinental Gas Pipe Line Company, LLC, Rockaway Delivery Lateral and Northeast Connector Projects (CP13-36, CP13-132)”. Federal Energy Regulatory Commission. 8 May 2014. Retrieved 4 October 2026.
  3. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  4. “Notification of In-Service, Northeast Connector Project (CP13-132)”. Transcontinental Gas Pipe Line Company, LLC (filed with FERC). 4 December 2014. Retrieved 4 October 2026.
  5. “Notification of Commencement of Construction, Northeast Connector Project (CP13-132)”. Transcontinental Gas Pipe Line Company, LLC (filed with FERC). 9 June 2014. Retrieved 4 October 2026.
  6. “Construction Cost Report, Northeast Connector Project (CP13-132)”. Transcontinental Gas Pipe Line Company, LLC (filed with FERC). 28 May 2015. Retrieved 4 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.