McCleary Well Conversion Project

From the ProvenHand pipeline wiki

McCleary Well Conversion Project is a natural gas pipeline conversion in Iowa, operated by Northern Natural Gas Company. Construction began in 2016.

McCleary Well Conversion Project
General information
Project typeConversion[1]
CommodityNatural gas[1]
Owner and operator
StateIowa[1]
CountiesDallas[1]
Construction startedAugust 2016[3]
FERC docketCP16-463[2]
Contractors
Technical information
Cost$1,500,000[1]
On ProvenHand
Hands listed0

McCleary Well Conversion Project is a natural gas pipeline conversion in Iowa, operated by Northern Natural Gas Company. Construction began in 2016.

Contractorsedit

ContractorWorkYears
T&C Consulting[4]Well workover (logging, re-perforation, fracturing, new tubing, casing pressure test)19 June 2017 – 22 June 2017

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on McCleary Well Conversion Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “Environmental Assessment Report, Northern Natural Gas prior notice, McCleary Well Conversion Project (CP16-463)”. FERC. 1 August 2016. Retrieved 4 October 2026.
  2. “FERC eLibrary docket CP16-463”. Federal Energy Regulatory Commission. 20 May 2016. Retrieved 3 October 2026.
  3. “Weekly Environmental Inspector Report No. 1, McCleary #1 Well Conversion Project (CP16-463)”. Northern Natural Gas Company (filed with FERC). 29 August 2016. Retrieved 4 October 2026.
  4. “Weekly Environmental Inspector Report No. 16, McCleary #1 Well Conversion Project (CP16-463)”. Northern Natural Gas Company (filed with FERC). 30 June 2017. Retrieved 4 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.