Nueva Era Dos Border Crossing is a natural gas pipeline in Texas, operated by Nueva Era Dos, LLC. It runs 0.7 miles of 36" pipe.

Nueva Era Dos Border Crossing
Also calledNueva Era Dos Pipeline Project[1]
General information
KindPipeline project[2]
Project typeNew build[1]
StatusProposed[1] or Approved[3][sources disagree]
CommodityNatural gas[1]
Owner and operator
Operator
StateTexas[1][4]
CountiesMaverick[3]
Approved29 May 2026[3][4]
FERC docketCP25-527[2]
Technical information
Length0.7 mi[1][4]
Pipe size36"[1][3]
Capacity1000 MMcf/d additional capacity (EIA)[1] or design capacity of one billion standard cubic feet per day[3][sources disagree]
On ProvenHand
Hands listed0

Nueva Era Dos Border Crossing is a natural gas pipeline in Texas, operated by Nueva Era Dos, LLC. It runs 0.7 miles of 36" pipe.

Crossings

FeatureMethod
Rio Grande[5]HDD

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Capacity
  • 1000 MMcf/d additional capacity (EIA)[1]
  • design capacity of one billion standard cubic feet per day[3]
Status

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Nueva Era Dos Border Crossing? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  2. “FERC eLibrary docket CP25-527”. Federal Energy Regulatory Commission. 24 July 2025. Retrieved 3 October 2026.
  3. “Order Issuing Presidential Permit and Granting Authorization Under Section 3, Nueva Era Dos, LLC (CP25-527)”. Federal Energy Regulatory Commission. 29 May 2026. Retrieved 4 October 2026.
  4. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  5. “Environmental Assessment, Nueva Era Dos Pipeline Project (CP25-527)”. Federal Energy Regulatory Commission. 30 January 2026. Retrieved 4 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.