Paiute 2007 Expansion

From the ProvenHand pipeline wiki

Sources disagree on some of this page's facts. Each value is shown with its sources; see Sources disagree.

Paiute 2007 Expansion is a natural gas pipeline expansion in Nevada, operated by Paiute Pipeline Company. It was built and entered service in 2007. It runs 4.3 miles of 20" pipe.

Paiute 2007 Expansion
General information
KindPipeline project[1]
Project typeExpansion[1]
StatusIn service[1]
CommodityNatural gas[1]
Operator
Owner and operator
StateNevada[1]
CountiesCarson City, Douglas, Lyon[3]
Construction started23 July 2007[4]
In serviceNovember 2007[1]
FERC docketCP07-102[2]
Technical information
Length4.3 mi[1]
Pipe size20"[1]
Capacity8.9 MMcf/d additional capacity (EIA)[1]
Capacity added8,913 Dth/d of additional firm transportation service capacity[3]
Cost$5.27 million (EIA estimate; no dollar year given)[1] or total cost of all of the 2007 Expansion Project facilities is estimated to be $5,273,000 (2007)[3][sources disagree]
On ProvenHand
Hands listed0

Paiute 2007 Expansion is a natural gas pipeline expansion in Nevada, operated by Paiute Pipeline Company. It was built and entered service in 2007. It runs 4.3 miles of 20" pipe.

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Cost
  • $5.27 million (EIA estimate; no dollar year given)[1]
  • total cost of all of the 2007 Expansion Project facilities is estimated to be $5,273,000 (2007)[3]

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Paiute 2007 Expansion? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  2. “FERC eLibrary docket CP07-102”. Federal Energy Regulatory Commission. 14 March 2007. Retrieved 3 October 2026.
  3. “Notice of Paiute Pipeline Co's 3/14/07 prior notice request for its 2007 Expansion Project (CP07-102)”. Federal Energy Regulatory Commission. 22 March 2007. Retrieved 4 October 2026.
  4. “Notice that construction of the authorized facilities commenced on 7/23/07 (CP07-102), eLibrary filing description”. Paiute Pipeline Company (filed with FERC). 21 September 2007. Retrieved 4 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.