Palmerton Loop is a pipeline loop in Pennsylvania, operated by Williams Transco. Construction began in 2013. It runs 3.2 miles of 42" pipe.
| Palmerton Loop | |
|---|---|
| General information | |
| Kind | Pipeline project[1] |
| Project type | Loop[1] |
| Operator | Williams Transco[1] |
| Owner | |
| Part of | Northeast Supply Link Expansion[2] |
| State | Pennsylvania[1] |
| Construction started | 1 April 2013[3] |
| Contractors | |
| Technical information | |
| Length | 3.2 mi[1] |
| Pipe size | 42"[1] |
| On ProvenHand | |
| Hands listed | 0 |
Palmerton Loop is a pipeline loop in Pennsylvania, operated by Williams Transco. Construction began in 2013. It runs 3.2 miles of 42" pipe.
Contractorsedit
| Contractor | Work | Scope | Years |
|---|---|---|---|
| U.S. Pipeline, Inc.[1] | Prime | 3.17 miles of 42-inch pipeline looping | 1 January 2013 |
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Palmerton Loop? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “Recent Projects - U.S. Pipeline (project map)”. U.S. Pipeline, Inc. Retrieved 3 October 2026.
- “Transcontinental Gas Pipe Line Company, LLC information on the Palmerton Loop Direct Pipe Installation, Northeast Supply Link Project (CP12-30)”. Transcontinental Gas Pipe Line Company, LLC (filed with FERC). 25 May 2012. Retrieved 4 October 2026.
- “US Pipeline Project Updates, June 18, 2013 (archive 2013-08-30)”. U.S. Pipeline, Inc. 18 June 2013. Archived from the original on 30 August 2013. Retrieved 6 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.