Rahway River Line 2 Pipeline Replacement Project
From the ProvenHand pipeline wiki
Rahway River Line 2 Pipeline Replacement Project is a natural gas pipeline replacement in New Jersey, operated by Texas Eastern Transmission, LP. Construction began in 2024.
| Rahway River Line 2 Pipeline Replacement Project | |
|---|---|
| General information | |
| Kind | Pipeline project[1] |
| Project type | Replacement[2] |
| Status | In service[3] |
| Commodity | Natural gas[1] |
| Owner and operator | |
| State | New Jersey[1] |
| Counties | Middlesex, Union[1] |
| Construction started | May 2024[4] |
| FERC docket | CP24-31[2] |
| Technical information | |
| Pipe size | 20"[1] |
| Cost | $18.7 million[1] |
| On ProvenHand | |
| Hands listed | 0 |
Rahway River Line 2 Pipeline Replacement Project is a natural gas pipeline replacement in New Jersey, operated by Texas Eastern Transmission, LP. Construction began in 2024.
Crossings
| Feature | Method |
|---|---|
| Rahway River[1] | HDD |
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Rahway River Line 2 Pipeline Replacement Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “Environmental Assessment Report, Rahway River Line 2 Pipeline Replacement Project (CP24-31)”. FERC. 26 February 2024. Retrieved 4 October 2026.
- “FERC eLibrary docket CP24-31”. Federal Energy Regulatory Commission. 18 December 2023. Retrieved 3 October 2026.
- “Weekly Status Report No. 46 (June 26 to July 30, 2025), Rahway River Line 2 Pipeline Replacement Project (CP24-31)”. Texas Eastern Transmission, LP (filed with FERC). 31 July 2025. Retrieved 4 October 2026.
- “Weekly Status Report No. 1 (May 13 to 21, 2024), Rahway River Line 2 Pipeline Replacement Project (CP24-31)”. Texas Eastern Transmission, LP (filed with FERC). 22 May 2024. Retrieved 4 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.