Rendezvous Gas Services CP05-40 is a natural gas pipeline lateral in Wyoming, operated by Rendezvous Gas Services, L.L.C.. Construction began in 2006. It runs 20.8 miles of 20" pipe.
| Rendezvous Gas Services CP05-40 | |
|---|---|
| Also called | Rendezvous Phase V Project[1], Rendezvous Black Fork Lateral[2], Rendezvous Pipeline Lateral[2] |
| General information | |
| Kind | Pipeline project[2][3] |
| Project type | Lateral[2] |
| Status | In service[2][4] |
| Commodity | Natural gas[1][2] |
| Owner and operator | |
| Owners | |
| State | Wyoming[2][3] |
| Counties | Lincoln, Uinta[1][5] |
| Approved | 27 July 2005[1][3] |
| Construction started | 18 July 2006[6] |
| In service | 8 February 2007[2] or 15 November 2006[2][sources disagree] |
| FERC docket | CP05-40[3] |
| Contractors | |
| Technical information | |
| Length | 20.8 mi[1][2][3] |
| Pipe size | 20"[1][2] |
| Capacity | 300 MMcf/d (FERC project list)[3] or 330 million cubic feet per day[6] or 330 MMcf/d additional capacity (EIA)[2][sources disagree] |
| Cost | $11.3 million estimated cost[1][2] or $35 million pipeline[6][sources disagree] |
| On ProvenHand | |
| Hands listed | 0 |
Rendezvous Gas Services CP05-40 is a natural gas pipeline lateral in Wyoming, operated by Rendezvous Gas Services, L.L.C.. Construction began in 2006. It runs 20.8 miles of 20" pipe.
Contractorsedit
| Contractor | Work | Scope |
|---|---|---|
| Jomax[7] | construction contractor, scope not stated | the pipeline company's contractor during construction (yard use for support activities) |
Sources disagree
These sources give different values for the same fact. Each value is listed with the sources that give it.
| Fact | Values given |
|---|---|
| Capacity | |
| Cost | |
| In service | |
| In service |
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Rendezvous Gas Services CP05-40? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “Order Issuing Certificates, Rendezvous Gas Services, L.L.C. (CP05-40, CP05-41)”. FERC. 27 July 2005. Retrieved 4 October 2026.
- “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
- “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
- “Notification of commencement of service of Rendezvous Pipeline Company, LLC (CP05-40 et al.)”. Rendezvous Pipeline Company, LLC (filed with FERC). 13 February 2007. Retrieved 4 October 2026.
- “Rendezvous Gas Services, L.L.C. and Rendezvous Pipeline Company, L.L.C.; Notice of Applications (CP06-62-000, CP06-63-000, CP06-65-000)”. Federal Energy Regulatory Commission (Federal Register, Vol. 71, No. 38, p. 9809). 27 February 2006. Retrieved 4 October 2026.
- “Questar Gas Management Begins Construction on Wyoming Natural Gas Pipeline”. Industrial Info Resources. 18 August 2006. Retrieved 4 October 2026.
- “Request to modify yard approval so its contractor can use the yards during construction (CP05-40), eLibrary entry”. Rendezvous Pipeline Company, LLC (filed with FERC). 31 July 2006. Retrieved 4 October 2026.