Rendezvous Gas Services CP05-40

From the ProvenHand pipeline wiki

Sources disagree on some of this page's facts. Each value is shown with its sources; see Sources disagree.

Rendezvous Gas Services CP05-40 is a natural gas pipeline lateral in Wyoming, operated by Rendezvous Gas Services, L.L.C.. Construction began in 2006. It runs 20.8 miles of 20" pipe.

Rendezvous Gas Services CP05-40
Also calledRendezvous Phase V Project[1], Rendezvous Black Fork Lateral[2], Rendezvous Pipeline Lateral[2]
General information
KindPipeline project[2][3]
Project typeLateral[2]
StatusIn service[2][4]
CommodityNatural gas[1][2]
Owner and operator
Owners
StateWyoming[2][3]
CountiesLincoln, Uinta[1][5]
Approved27 July 2005[1][3]
Construction started18 July 2006[6]
In service8 February 2007[2] or 15 November 2006[2][sources disagree]
FERC docketCP05-40[3]
Contractors
Technical information
Length20.8 mi[1][2][3]
Pipe size20"[1][2]
Capacity300 MMcf/d (FERC project list)[3] or 330 million cubic feet per day[6] or 330 MMcf/d additional capacity (EIA)[2][sources disagree]
Cost$11.3 million estimated cost[1][2] or $35 million pipeline[6][sources disagree]
On ProvenHand
Hands listed0

Rendezvous Gas Services CP05-40 is a natural gas pipeline lateral in Wyoming, operated by Rendezvous Gas Services, L.L.C.. Construction began in 2006. It runs 20.8 miles of 20" pipe.

Contractorsedit

ContractorWorkScope
Jomax[7]construction contractor, scope not statedthe pipeline company's contractor during construction (yard use for support activities)

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Capacity
  • 300 MMcf/d (FERC project list)[3]
  • 330 million cubic feet per day[6]
  • 330 MMcf/d additional capacity (EIA)[2]
Cost
  • $11.3 million estimated cost[1][2]
  • $35 million pipeline[6]
In service
  • 8 February 2007[2]
  • 15 November 2006[2]
In service

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Rendezvous Gas Services CP05-40? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “Order Issuing Certificates, Rendezvous Gas Services, L.L.C. (CP05-40, CP05-41)”. FERC. 27 July 2005. Retrieved 4 October 2026.
  2. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  3. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  4. “Notification of commencement of service of Rendezvous Pipeline Company, LLC (CP05-40 et al.)”. Rendezvous Pipeline Company, LLC (filed with FERC). 13 February 2007. Retrieved 4 October 2026.
  5. “Rendezvous Gas Services, L.L.C. and Rendezvous Pipeline Company, L.L.C.; Notice of Applications (CP06-62-000, CP06-63-000, CP06-65-000)”. Federal Energy Regulatory Commission (Federal Register, Vol. 71, No. 38, p. 9809). 27 February 2006. Retrieved 4 October 2026.
  6. “Questar Gas Management Begins Construction on Wyoming Natural Gas Pipeline”. Industrial Info Resources. 18 August 2006. Retrieved 4 October 2026.
  7. “Request to modify yard approval so its contractor can use the yards during construction (CP05-40), eLibrary entry”. Rendezvous Pipeline Company, LLC (filed with FERC). 31 July 2006. Retrieved 4 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.