Rockaway Delivery Lateral Project is a natural gas pipeline in New York, operated by Transcontinental Gas Pipe Line Company, LLC. Construction began in 2014. It runs 3.2 miles of 26" pipe.

Rockaway Delivery Lateral Project
Also calledTransco Rockaway Delivery Project[1]
General information
KindPipeline project[1]
Project typeNew build[2] or Lateral[3][sources disagree]
StatusIn service[2][4]
CommodityNatural gas[2]
Owner and operator
StateNew York[1][2]
CountiesKings, Queens[5]
Approved8 May 2014[1][5]
Construction started9 June 2014[6]
In service14 May 2015[2] or 15 May 2015[4][sources disagree]
FERC docketCP13-36[1]
FERC pre-filing docketPF09-8[1]
Technical information
Length3.2 mi[1][2][5]
Pipe size26"[2][5]
Capacity647 MMcf/d (FERC project list)[1][2]
Cost$12 million (EIA estimate; no dollar year given)[2] or approximately $182.8 million (Transco's estimate in the certificate order)[5][sources disagree]
On ProvenHand
Hands listed0

Rockaway Delivery Lateral Project is a natural gas pipeline in New York, operated by Transcontinental Gas Pipe Line Company, LLC. Construction began in 2014. It runs 3.2 miles of 26" pipe.

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Project type
Cost
  • $12 million (EIA estimate; no dollar year given)[2]
  • approximately $182.8 million (Transco's estimate in the certificate order)[5]
In service

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Rockaway Delivery Lateral Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  2. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  3. “FERC eLibrary docket CP13-36”. Federal Energy Regulatory Commission. 12 June 2012. Retrieved 3 October 2026.
  4. “Notification of In-Service, Rockaway Delivery Lateral Project (CP13-36)”. Transcontinental Gas Pipe Line Company, LLC (filed with FERC). 18 May 2015. Retrieved 4 October 2026.
  5. “Order Issuing Certificates and Granting Abandonment, Transcontinental Gas Pipe Line Company, LLC, Rockaway Delivery Lateral and Northeast Connector Projects (CP13-36, CP13-132)”. Federal Energy Regulatory Commission. 8 May 2014. Retrieved 4 October 2026.
  6. “Notification of Commencement of Construction, Rockaway Delivery Lateral Project (CP13-36)”. Transcontinental Gas Pipe Line Company, LLC (filed with FERC). 10 June 2014. Retrieved 4 October 2026.