SONAT North Main Loop Replacement is a natural gas pipeline in Alabama, operated by Southern Natural Gas Company, L.L.C.. It was built and entered service in 2007.

SONAT North Main Loop Replacement
Also called2007 Alabama Abandonment & Replacement Project[1]
General information
KindPipeline project[2]
Project typeExpansion[3] or Replacement[4][sources disagree]
StatusIn service[3]
CommodityNatural gas[3]
Owner and operator
StateAlabama[2][3]
CountiesTuscaloosa[4]
Approved16 April 2007[2]
Construction started7 June 2007[5]
In service17 September 2007[3]
FERC docketCP07-28[2]
Technical information
Length6.8 mi[2] or 9.6 mi[3][sources disagree]
Pipe size24"[4]
Cost$10.4 million (EIA estimate; no dollar year given)[3]
On ProvenHand
Hands listed0

SONAT North Main Loop Replacement is a natural gas pipeline in Alabama, operated by Southern Natural Gas Company, L.L.C.. It was built and entered service in 2007.

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Project type
Length

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on SONAT North Main Loop Replacement? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC eLibrary docket CP07-28”. Federal Energy Regulatory Commission. 1 December 2006. Retrieved 3 October 2026.
  2. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  3. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  4. “Order Approving Abandonment and Issuing Certificate, Southern Natural Gas Company (CP07-28)”. Federal Energy Regulatory Commission. 16 April 2007. Retrieved 4 October 2026.
  5. “Letter notifying that construction commenced, CP07-28, eLibrary record”. Southern Natural Gas Company (filed with FERC). 18 June 2007. Retrieved 4 October 2026.