Stratton Ridge Expansion is a natural gas pipeline expansion in Louisiana and Texas, operated by Texas Eastern Transmission, LP. Construction began in 2018.

Stratton Ridge Expansion
General information
KindPipeline project[1]
Project typeExpansion[2]
StatusIn service[2][3]
CommodityNatural gas[2]
Owners and operators
Operator
Facility project
StatesLouisiana, Texas[2]
CountiesBrazoria, Chambers, San Jacinto, Shelby[6]
Approved6 April 2018[1][6]
Construction started1 May 2018[7]
In service22 March 2019[2] or 18 March 2019[3][sources disagree]
FERC docketsCP17-56[1], CP17-57[1]
Technical information
Pipe size30"[6]
Capacity500 MMcf/d additional capacity (EIA)[2]
Capacity added322,000 Dth/day of firm transportation service[6]
Cost$200 million (EIA estimate; no dollar year given)[2]
On ProvenHand
Hands listed0

Stratton Ridge Expansion is a natural gas pipeline expansion in Louisiana and Texas, operated by Texas Eastern Transmission, LP. Construction began in 2018.

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
In service
  • 22 March 2019[2]
  • 18 March 2019[3]

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Stratton Ridge Expansion? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  2. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  3. “Notice of Commencement of Service, Stratton Ridge Expansion Project (CP17-56)”. Texas Eastern Transmission, LP (filed with FERC). 22 March 2019. Retrieved 4 October 2026.
  4. “FERC eLibrary docket CP17-57”. Federal Energy Regulatory Commission. 3 February 2017. Retrieved 3 October 2026.
  5. “FERC eLibrary docket CP17-56”. Federal Energy Regulatory Commission. 3 February 2017. Retrieved 3 October 2026.
  6. “Order Issuing Certificates, Texas Eastern Transmission, LP and Brazoria Interconnector Gas Pipeline LLC, Stratton Ridge Expansion Project (CP17-56, CP17-57)”. Federal Energy Regulatory Commission. 6 April 2018. Retrieved 4 October 2026.
  7. “Monthly Status Report No. 1, Stratton Ridge Expansion Project (CP17-56)”. Texas Eastern Transmission, LP (filed with FERC). 23 May 2018. Retrieved 4 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.