Tennessee Gas Pipeline Northeast Upgrade Project

From the ProvenHand pipeline wiki

Sources disagree on some of this page's facts. Each value is shown with its sources; see Sources disagree.

Tennessee Gas Pipeline Northeast Upgrade Project is a natural gas pipeline expansion in Pennsylvania and New Jersey, operated by Tennessee Gas Pipeline (Kinder Morgan).[1]

Tennessee Gas Pipeline Northeast Upgrade Project
Also calledNortheast Upgrade[4], NEUP, TGP Northeast Upgrade
General information
Project typeExpansion[3]
StatusIn service[3]
CommodityNatural gas[3]
OperatorTennessee Gas Pipeline (Kinder Morgan)
Owner and operator
StatesPennsylvania, New Jersey[3][4]
CountiesNew Jersey: Bergen, Passaic, Sussex
Pennsylvania: Bradford, Pike, Susquehanna, Wayne
[5]
Approved29 May 2012[4][5]
In service5 December 2013[3] or 1 November 2013[6][sources disagree]
FERC docketCP11-161[4]
FERC pre-filing docketPF10-23[4]
Technical information
Length40.3 mi[3][5] or 39.5 mi[4][sources disagree]
Pipe size24 in[3] or 30 in[5][sources disagree]
Capacity636 MMcf/d (FERC project list)[3][4]
Horsepower added22,310 hp[5]
Cost$500 million (EIA estimate; no dollar year given)[3][6]
On ProvenHand
Hands listed0

Tennessee Gas Pipeline Northeast Upgrade Project is a natural gas pipeline expansion in Pennsylvania and New Jersey, operated by Tennessee Gas Pipeline (Kinder Morgan).[1]

Crossings

FeatureMethod
Delaware River[5]HDD
Monksville Reservoir[5]HDD
Susquehanna River[7]HDD

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Diameters
In service
  • 5 December 2013[3]
  • 1 November 2013[6]
Length

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Tennessee Gas Pipeline Northeast Upgrade Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. sec.gov · kmi-2013x10k.htm
  2. sec.gov · kmi-20121231x10k.htm
  3. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  4. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  5. “Order Issuing Certificate and Approving Abandonment, Northeast Upgrade Project (CP11-161)”. Federal Energy Regulatory Commission. 29 May 2012. Retrieved 4 October 2026.
  6. “Tennessee Gas Pipeline Places Projects in Service to Move More Marcellus Shale Natural Gas”. Kinder Morgan (Business Wire release). 1 November 2013. Retrieved 3 October 2026.
  7. “Implementation Plan and Affirmative Statement, Northeast Upgrade Project (CP11-161), construction schedule”. Tennessee Gas Pipeline Company, L.L.C. (filed with FERC). 8 August 2012. Retrieved 4 October 2026.