Terra Alta Compressor Station Replacement

From the ProvenHand pipeline wiki

Terra Alta Compressor Station Replacement is a natural gas facility project in West Virginia, operated by Columbia Gas Transmission, LLC.

Terra Alta Compressor Station Replacement
General information
KindFacility project[1]
Project typeRebuild[2]
StatusApproved[1]
CommodityNatural gas[1]
Owner and operator
StateWest Virginia[1]
CountiesPreston[1]
FERC docketCP22-36[2]
Technical information
Units added3 × Ariel KBT-6 (electric motor drive, reciprocating compressor, 2,250 hp each)[1]
Cost$65.3 million[1]
On ProvenHand
Hands listed0

Terra Alta Compressor Station Replacement is a natural gas facility project in West Virginia, operated by Columbia Gas Transmission, LLC.

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Terra Alta Compressor Station Replacement? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “Environmental Assessment Report, Section 2.55(b)(3) Advance Notification of Replacement of Facilities, Terra Alta Compressor Station (CP22-36)”. Federal Energy Regulatory Commission. 19 January 2022. Retrieved 3 October 2026.
  2. “FERC eLibrary docket CP22-36”. Federal Energy Regulatory Commission. 4 January 2022. Retrieved 3 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.