TP-4555 Bare Pipe Replacement Project

From the ProvenHand pipeline wiki

TP-4555 Bare Pipe Replacement Project is a natural gas pipeline replacement in Pennsylvania, operated by Equitrans, L.P.. Construction began in 2020. It runs 3.9 miles.

TP-4555 Bare Pipe Replacement Project
General information
KindPipeline project[1]
Project typeReplacement[1]
CommodityNatural gas[2]
Owner and operator
StatePennsylvania[2]
CountiesWestmoreland[2]
Construction started12 May 2020[3]
FERC docketCP19-218[1]
Contractors
Technical information
Length3.9 mi[2]
On ProvenHand
Hands listed0

TP-4555 Bare Pipe Replacement Project is a natural gas pipeline replacement in Pennsylvania, operated by Equitrans, L.P.. Construction began in 2020. It runs 3.9 miles.

Contractorsedit

ContractorWorkScope
Frontier Environmental Services[3]PrimeNamed as the pipeline contractor in Equitrans' weekly environmental inspector report no. 1 (mobilized May 11, 2020; official construction start May 12, 2020)

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on TP-4555 Bare Pipe Replacement Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC eLibrary docket CP19-218”. Federal Energy Regulatory Commission. 24 April 2019. Retrieved 3 October 2026.
  2. “Equitrans, L.P.; Notice of Request Under Blanket Authorization (CP19-218)”. Federal Energy Regulatory Commission (Federal Register notice). 13 May 2019. Retrieved 4 October 2026.
  3. “Weekly environmental inspector report no. 1, TP-4555 Bare Pipe Replacement Project (CP19-218)”. Equitrans, L.P. (filed with FERC). 15 May 2020. Retrieved 4 October 2026.