Transco Hillabee Expansion

From the ProvenHand pipeline wiki

This is an old revision of this page, as edited by ProvenHand at 17:10, 3 October 2026 (Imported from public sources (FERC, EIA, operators, contractors, trade press)). It may differ significantly from the current version.

Transco Hillabee Expansion is a natural gas pipeline in Alabama, operated by Williams (Transco). Construction began in 2016 and the line entered service in 2020. It runs 43.6 miles of 42", 48" pipe.[1]

Transco Hillabee Expansion
Also calledHillabee Expansion Project, Hillabee
General information
CommodityNatural gas
OperatorWilliams (Transco)
StateAlabama
Construction started2016
In service2020
Contractors
  • Price Gregory
Technical information
Length43.6 mi
Pipe size42", 48"
On ProvenHand
Hands listed0

Transco Hillabee Expansion is a natural gas pipeline in Alabama, operated by Williams (Transco). Construction began in 2016 and the line entered service in 2020. It runs 43.6 miles of 42", 48" pipe.[1]

Contractorsedit

ContractorScope
Price Gregory[3]Phase I loops (5 mi of 48-inch, 15 mi of 42-inch, 2016-2017) and Phase II (10.3 mi of 42-inch, 2019)

Referencesedit

  1. nsenergybusiness.com
  2. worldpipelines.com
  3. pricegregory.com · Price-Gregory-Completed-Pipeline-Project
  4. industrialinfo.com