Union Meter Station Upgrade Project

From the ProvenHand pipeline wiki

Union Meter Station Upgrade Project is a pipeline project, operated by Northwest Pipeline LLC. It entered service in 2016.

Union Meter Station Upgrade Project
General information
StatusIn service[1]
Owner and operator
CountiesUnion[3]
Approved4 June 2015[4]
In service15 January 2016[1]
FERC docketCP15-110[2]
Technical information
Capacityapproximately 5,500,000 standard cubic feet per day (station capacity after the upgrade)[3]
Cost$553,000 (EA cost line; no dollar year given)[3]
On ProvenHand
Hands listed0

Union Meter Station Upgrade Project is a pipeline project, operated by Northwest Pipeline LLC. It entered service in 2016.

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Union Meter Station Upgrade Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “Quarterly Status Report No. 1, Union Meter Station Upgrade Project (CP15-110)”. Northwest Pipeline LLC (filed with FERC). 19 April 2016. Retrieved 4 October 2026.
  2. “FERC eLibrary docket CP15-110”. Federal Energy Regulatory Commission. 6 March 2015. Retrieved 3 October 2026.
  3. “Environmental Assessment, Union Meter Station Upgrade Project (CP15-110)”. Federal Energy Regulatory Commission. 21 May 2015. Retrieved 4 October 2026.
  4. “Request to place facilities into service, Union Meter Station Upgrade (CP15-110)”. Northwest Pipeline LLC (filed with FERC). 7 January 2016. Retrieved 4 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.