Virginia Reliability Project

From the ProvenHand pipeline wiki

Sources disagree on some of this page's facts. Each value is shown with its sources; see Sources disagree.

Virginia Reliability Project is a natural gas pipeline expansion in Virginia, operated by Columbia Gas Transmission, LLC. Construction began in 2024. It runs 49 miles of 24" pipe.

Virginia Reliability Project
General information
KindPipeline project[1]
Project typeExpansion[2]
StatusIn service[2]
CommodityNatural gas[2]
Owner and operator
Operator
Facility projects
StateVirginia[1][2]
CountiesChesapeake (city), Greensville, Isle of Wight, Prince George, Southampton, Suffolk (city), Surry, Sussex[3]
Approved16 November 2023[1][3]
Construction started15 July 2024[4]
In service9 December 2025[2] or 1 November 2025[5][sources disagree]
LaborUnion[6][7]
FERC docketCP22-503[1]
FERC pre-filing docketPF22-3[8]
Contractors
Technical information
Length49 mi[1][2]
Pipe size24"[2]
Capacity100 MMcf/d (FERC project list)[1][2]
Cost$500 million (EIA estimate; no dollar year given)[2] or approximately $917,925,527[3][sources disagree]
On ProvenHand
Hands listed0

Virginia Reliability Project is a natural gas pipeline expansion in Virginia, operated by Columbia Gas Transmission, LLC. Construction began in 2024. It runs 49 miles of 24" pipe.

Contractorsedit

ContractorWorkScopeYears
Associated Pipe Line Contractors, Inc.[7][9]PrimeMainline contractor: 48 miles of 24-inch plus fabrication at Chesapeake, VA; about 25 miles of 24-inch in 2024 and the rest in 20251 January 2024 – 1 January 2025

Inspection

FirmScope
Accent Compliance, LLC[10]FERC third-party compliance monitoring

Crossings

FeatureMethod
Blackwater River HDD (VM-108, exit MP 11.9)[11]HDD
Coppahaunk Swamp HDD (VM-108 Segment 1, MP 1.8)[12]HDD
Military Highway and CSX HDD (VM-107 Segment 3B, MP 12.67 to MP 12.7)[13]HDD
Nansemond River HDD (VM-107 Segment 2, entry MP 6.6)[14]HDD
Roundtree North HDD (VM-107 Segment 2, exit MP 5.0)[15]HDD
Southern Branch Elizabeth River HDD[16]HDD
Western Branch Reservoir HDD (exit MP 2.2)[17]HDD

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Cost
  • $500 million (EIA estimate; no dollar year given)[2]
  • approximately $917,925,527[3]
In service
  • 9 December 2025[2]
  • 1 November 2025[5]

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Virginia Reliability Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  2. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  3. “Order Issuing Certificates and Approving Abandonment, Transcontinental Gas Pipe Line Company, LLC and Columbia Gas Transmission, LLC (CP22-502, CP22-503)”. Federal Energy Regulatory Commission. 16 November 2023. Retrieved 3 October 2026.
  4. “Notification of commencement of construction, Virginia Reliability Project (CP22-503)”. Columbia Gas Transmission, LLC (filed with FERC). 18 July 2024. Retrieved 3 October 2026.
  5. “Notice of commencement of full service, Virginia Reliability Project (CP22-503)”. Columbia Gas Transmission, LLC (filed with FERC). 7 November 2025. Retrieved 3 October 2026.
  6. “TC Energy celebrates the Virginia Reliability Project, enhancing energy security”. TC Energy. 24 November 2025. Retrieved 3 October 2026.
  7. “Blue Light Reports, September/October 2024”. Pipeliners Local Union 798. September 2024. Retrieved 6 October 2026.
  8. “FERC eLibrary docket CP22-503”. Federal Energy Regulatory Commission. 24 August 2022. Retrieved 3 October 2026.
  9. “Blue Light Reports, November/December 2025”. Pipeliners Local Union 798. November 2025. Retrieved 6 October 2026.
  10. “Executed Memorandum of Understanding with Accent Compliance, LLC (third-party compliance monitoring), Virginia Reliability Project (CP22-503)”. Columbia Gas Transmission, LLC (filed with FERC). 27 June 2024. Retrieved 3 October 2026.
  11. “Environmental Compliance Monitoring Weekly Summary Report, Apr 2025, Virginia Reliability Project (CP22-503)”. FERC (compliance monitor weekly report). 8 May 2025. Retrieved 3 October 2026.
  12. “Environmental Compliance Monitoring Weekly Summary Report, Aug 26-Sep 1, 2024, Virginia Reliability Project (CP22-503)”. FERC (compliance monitor weekly report). 20 September 2024. Retrieved 3 October 2026.
  13. “Environmental Compliance Monitoring Weekly Summary Report, Dec 2024, Virginia Reliability Project (CP22-503)”. FERC (compliance monitor weekly report). 19 December 2024. Retrieved 3 October 2026.
  14. “Environmental Compliance Monitoring Weekly Summary Report, Nov 2025, Virginia Reliability Project (CP22-503)”. FERC (compliance monitor weekly report). 14 November 2025. Retrieved 3 October 2026.
  15. “Environmental Compliance Monitoring Weekly Summary Report, Sep 2025, Virginia Reliability Project (CP22-503)”. FERC (compliance monitor weekly report). 17 September 2025. Retrieved 3 October 2026.
  16. “Implementation Plan, Virginia Reliability Project (CP22-503)”. Columbia Gas Transmission, LLC (filed with FERC). 29 January 2024. Retrieved 3 October 2026.
  17. “Environmental Compliance Monitoring Weekly Summary Report, late Sep 2025, Virginia Reliability Project (CP22-503)”. FERC (compliance monitor weekly report). 7 October 2025. Retrieved 3 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.