Wax Lake Remediation Project

From the ProvenHand pipeline wiki

Wax Lake Remediation Project is a pipeline lateral in Louisiana, operated by Columbia Gulf Transmission, LLC. Construction began in 2025.

Wax Lake Remediation Project
General information
KindPipeline project[1]
Project typeLateral[1]
StatusIn service[2]
Owner and operator
StateLouisiana[3]
CountiesSt. Mary[3]
Approved30 July 2024[4]
Construction started17 February 2025[4]
FERC docketCP24-471[1]
Technical information
Pipe size30"[3]
Cost$16,600,000[3]
On ProvenHand
Hands listed0

Wax Lake Remediation Project is a pipeline lateral in Louisiana, operated by Columbia Gulf Transmission, LLC. Construction began in 2025.

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Wax Lake Remediation Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC eLibrary docket CP24-471”. Federal Energy Regulatory Commission. 23 May 2024. Retrieved 3 October 2026.
  2. “Weekly Construction Status Report No. 25 (final, period beginning 08/04/2025), Wax Lake Remediation Project (CP24-471)”. Columbia Gulf Transmission, LLC (filed with FERC). 21 August 2025. Retrieved 3 October 2026.
  3. “Environmental Assessment Report, Columbia Gulf Wax Lake Remediation Project (CP24-471)”. Federal Energy Regulatory Commission (Office of Energy Projects). 29 July 2024. Retrieved 3 October 2026.
  4. “Weekly Construction Status Report No. 1 (2/17/2025 onward), Wax Lake Remediation Project (CP24-471)”. Columbia Gulf Transmission, LLC (filed with FERC). 26 February 2025. Retrieved 3 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.