West Leg 2024 Expansion Project
From the ProvenHand pipeline wiki
West Leg 2024 Expansion Project is a pipeline expansion in Minnesota and Nebraska, operated by Northern Natural Gas Company. It was built and entered service in 2024. It runs 4.5 miles of 16" pipe.
| West Leg 2024 Expansion Project | |
|---|---|
| General information | |
| Kind | Pipeline project[1] |
| Project type | Expansion[1] |
| Status | In service[2][3] |
| Owner and operator | |
| States | Minnesota, Nebraska[4] |
| Counties | Minnesota: Martin Nebraska: Dodge[4] |
| Construction started | 10 June 2024[5] |
| In service | 31 October 2024[3] |
| FERC docket | CP24-83[1] |
| Contractors | |
| Technical information | |
| Length | 4.5 mi[4] |
| Pipe size | 16"[4] |
| Capacity added | 12,960 dekatherms per day of peak winter volume (customer requests)[6] |
| Cost | $18,100,000[4] |
| On ProvenHand | |
| Hands listed | 0 |
West Leg 2024 Expansion Project is a pipeline expansion in Minnesota and Nebraska, operated by Northern Natural Gas Company. It was built and entered service in 2024. It runs 4.5 miles of 16" pipe.
Contractorsedit
| Contractor | Work | Scope |
|---|---|---|
| K & K, Inc.[5] | Prime | Construction of the 4.53-mile C-line extension (Martin County, MN) |
| Manhattan Pipeline, LLC[2] | Regulator station construction | Columbus branch line tie-over regulator station (Dodge County, NE) |
| Eagan, Field, and Nowak, Inc.[5] | Survey | Surveyed the project area (June 5 to June 8, 2024) |
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on West Leg 2024 Expansion Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “FERC eLibrary docket CP24-83”. Federal Energy Regulatory Commission. 7 March 2024. Retrieved 3 October 2026.
- “Weekly Environmental Inspector Report No. 28 (period 12/16/2024 to 12/22/2024), West Leg 2024 Expansion Project (CP24-83)”. Northern Natural Gas Company (filed with FERC). 23 December 2024. Retrieved 3 October 2026.
- “Supplement to Weekly Environmental Inspector Report No. 28, West Leg 2024 Expansion Project (CP24-83)”. Northern Natural Gas Company (filed with FERC). 23 December 2024. Retrieved 4 October 2026.
- “Environmental Assessment Report, Northern Natural Gas West Leg 2024 Expansion Project (CP24-83)”. Federal Energy Regulatory Commission (Office of Energy Projects). 16 May 2024. Retrieved 3 October 2026.
- “Weekly Environmental Inspector Report No. 1 (period ending 06/16/2024), West Leg 2024 Expansion Project (CP24-83)”. Northern Natural Gas Company (filed with FERC). 20 June 2024. Retrieved 3 October 2026.
- “Expansion Projects / West Leg 2024, Northern Natural Gas project page (archived 2024-04-14)”. Northern Natural Gas. 14 April 2024. Archived from the original on 14 April 2024. Retrieved 3 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.