Wisconsin 2006 Expansion Project is a natural gas pipeline expansion, operated by ANR Pipeline Company. It runs 6.9 miles of 16", 30" pipe.

Wisconsin 2006 Expansion Project
Also calledANR Wisconsin 2006 Expansion Project[1]
General information
KindPipeline project[1]
Project typeExpansion[2][3][4]
StatusIn service[2][5]
CommodityNatural gas[2][4]
Owner and operator
StateWI[1][4] or MI, WI[2][sources disagree]
Approved12 December 2005[1][4]
In service15 December 2006[2] or 9 November 2006[5][sources disagree]
FERC docketCP05-364[1]
Technical information
Length6.9 mi[1][2][4]
Pipe size16", 30"[2][4]
Capacity168.2 MMcf/d (FERC project list)[1][2]
Capacity addedadditional 168,241 Dth/d[4]
Horsepower added22,990 hp[4]
Cost$48.1 million (EIA estimate; no dollar year given)[2][4]
On ProvenHand
Hands listed0

Wisconsin 2006 Expansion Project is a natural gas pipeline expansion, operated by ANR Pipeline Company. It runs 6.9 miles of 16", 30" pipe.

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
In service
  • 15 December 2006[2]
  • 9 November 2006[5]
States

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Wisconsin 2006 Expansion Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  2. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  3. “FERC eLibrary docket CP05-364”. Federal Energy Regulatory Commission. 31 May 2005. Retrieved 3 October 2026.
  4. “Order issuing certificate, ANR Pipeline Company (Wisconsin 2006 Expansion Project, CP05-364)”. Federal Energy Regulatory Commission. 12 December 2005. Retrieved 4 October 2026.
  5. “Notification that the Janesville compressor unit was placed in service 11/1/06 and the Goodman Compressor Station 11/9/06 (CP05-364)”. Federal Energy Regulatory Commission. 9 November 2006. Retrieved 4 October 2026.